Should the primary fuel need to be changed to LP gas, the fuel system needs to be reconfigured. See Section 1.9 for instructions on reconfiguration of the fuel system.

Recommended fuels should have a Btu content of at

least 1,000 Btus per cubic foot for natural gas; or at least 2,520 Btus per cubic foot for LP gas. Ask the fuel supplier for the Btu content of the fuel.

Required fuel pressure for natural gas is 5 inches to 7 inches water colum (0.18 to 0.25 psi); and for liquid propane, 11 inches to 14 inches of water column (0.4 to 0.5 psi).

NOTE:

Any piping used to connect the generator to the fuel supply should be of adequate size to ensure the fuel pressure NEVER drops below 4 inches water colum for natural gas or 10 inches water column for liquid propane for all load ranges.

1.8FUEL CONSUMPTION

*Natura{ gas is in cubic feet per hour.

**LP is in gatlons per hour/cubic feet per hour. **_ Values given are approximate

Model #

Nat.

Gas (*)

LP Vapor

(**)

 

1/2 Load

FullLoad

1/2 Load

Full Load

6/7 kW

66

119

O.82/30

1.47/54

12 kW

152

215

1.53/56

2.08/76

13/15 kW

156

220

1.58/58

2.40/88

1.9.2 GENERATOR

_lnstall the generator set, in its protective enclosure, outdoors, where adequate cooling and ventilating air is always available. Consider these factors:

Install the unit where air inlet and outlet openings will not become obstructed by leaves, grass, snow, etc. If prevailing winds will cause blowing or drifting, consider using a windbreak to protect the unit.

Install the generator on high ground where water levels will not rise and endanger it.

Allow sufficient room on all sides of the generator for maintenance and servicing. A good rule is to allow three feet of space on all sides.

Where strong prevailing winds blow from one direction, face the generator air inlet openings to the prevailing winds.

Install the generator as close as possible to the fuel supply, to reduce the length of piping.

Install the generator as close as possible to the

transfer switch. HOWEVER, REMEMBER THAT

LAWS OR CODES MAY REGULATE THE DISTANCE.

The genset must be installed on a level surface. The base frame must be level within two (2) inches all around.

13.3 TRANSFER SWITCH

_ Gaseous fuels such as natural gas and liquid propane (LP) gas are highly explosive. Even the

slightest spark can ignite such fuels and cause an explosion. No leakage of fuel is permitted. Natural gas, which is lighter than air, tends to

collect in high areas. LP gas is heavier than air and tends to settle in low areas.

1.9LOCATION

1.9.1 LIFTING THE GENERATOR

To lift the generator, insert pipe having sufficient strength and diameter through the lifting holes which are located near the unit's base (see Figure 1.1 and 1.2, page 5). You may also lift the unit using a hook and hoist method provided you utilize a spreader bar to ensure that the lifting lines clear the roof panel.

z_ When lifting or hoisting equipment is used, be careful not to contact overhead power lines.

_The .generator's weight of more than 300 pounds requires proper tools, equipment and qualified

personnel to be used in all phases of handling and unpacking.

1.9.3.17 kW, 12 kW and 15 kW Units

The transfer switch shipped with this generator is enclosed in a NEMA 1 enclosure. This type of enclosure is intended for indoor use only. Follow these rules:

Install the transfer switch indoors on a firm, sturdy supporting structure.

To prevent switch distortion, level the switch if necessary. This can be done by placing washers between the switch enclosure and mounting surface.

Never install the switch where water or any corrosive substance might drip onto the enclosure.

Protect the switch at all times against excessive moisture, dust, dirt, lint, construction grit and corrosive vapors.

oAwARN NcA-

_lf the AUTO/OFF/MANUAL switch is not set to its OFF position, the generator can crank and

start as soon as the battery cables are connected. If the utility power supply is not turned off, sparking can occur at the battery posts and cause an explosion.

Carrier7

Image 9
Contents Air-cooled, Prepackaged Automatic Standby Generators Operation and Maintenance ContentsHOW to Obtain Service IntroductionIntroduction General Hazards Safetyrules Important Safety InstructionsStandards Index Important Safety Instructions Safetyrules 12 ARC Fault Circuit Interrupter Protection UNPACKING/INSPECTION Protection Systems Gfci GeneratorSystem SET LED SpecificationsFuel Requirements GeneratorTransfer Switch Fuel ConsumptionLifting the Generator Battery Installation BatteryAUTO/OFF/MANUAL Using the AUTO/OFF/MANUAL Switch Figure BREAK-IN ProcedureAuto Position OFF PositionAutomatic Transfer Operation 1 12 Vdcaccessory OutletSequence of Automatic Operation 2 120 VAC Gfci OutletTransfer to Generator Power Source Transfer Back to Utility Power SourceManual Transfer Operation High Temperature Switch LOW OIL Pressure SwitchFuses Over CrankChecking the Engine OIL Level OIL Change ProcedureChanging the Engine OIL Engine OIL RecommendationsChanging the OIL Filter Changing the Engine AIR CleanerSpark Plugs 1 7 KW, 12 Kwand 15 KW GeneratorsAUTO/OFF/MANUAL switch is set to Battery MaintenanceRemoval from Service OUT of Service ProcedureReturn to Service Corrosion ProtectionService Schedule ServiceProcedure Frequency Problemcausecorrection Troubleshooting GuideWarranty CarrierAir-cooled 7 EW, 12 EW and 15 EW Generators 21 ! Murphy Drive Generac Power SYSTEMS, INCEmission Related Parts Include the Following Emission Control System WarrantyCatalog NO. OMASPAS07-2