hydro turbine

Electronic Load

Controller - ELC

Main network or house

distribution board

Ballast load

220VAC house supply

ABC

To connect the electrical components, please follow these steps:

The electrics should be installed by persons competent in mains voltage wiring. This system operates on a switched neutral basis. Neutral and phase connections to the load elements should be treated as live at all times!

1.Install the control box (A) in a convenient location that is protected from rain and sun. This may be either in a powerhouse along with the turbine or else in a house at the user’s end.

2.Earth-bond (ground) PowerPal. Do this by attaching one end of a suitable length of wire to PowerPal and the other end to a metal object or metal stake in the ground nearby PowerPal. Although the risk of electric shock is already low, this earth-bonding is still best practice.

3.Connect the generator to the control box (B). All wiring from the generator to the control box, from the control box to the user load and from the control box to the ballast load should be done using insulated multistrand copper wire, the size of which is given in the Technical Specifications part of this manual. The following wiring diagram applies:

PowerPalT2 Turgo 9

Image 9
Contents Models MHG-T2 Safety First Read this FirstOperating Cautions System Diagram Powerpal ComponentsForebay, or water Measuring Gross Head Selecting a SiteSite Preparation Measuring FlowPowerPal T2 Turgo System Installation Mechanical AspectsElectrical Aspects ABC Hydro turbineOperation Greasing the Bearings Care and MaintenanceChanging the Bearings and Seal Troubleshooting Power output has been falling recently MHG-T2 Technical SpecificationsAppendix a Forebay Design Output watts Powerpal T2 Turgo Models