Table 2-1. Trouble-Shooting Checks.
| CHECK IN NUMERICAL SEQUENCE | ||
PROBLEM |
|
|
|
1 | 2 | 3 | |
| OPERATION |
| VOLTAGE |
Hold Transfer Test switch 15 | Starting control must be in the |
| |
not start when the Transfer | seconds or the outage must | automatic position. Batteries |
|
Control switch is turned and | be long enough to allow for | must be charged and | |
held in Transfer Test position | Feature 1C time delay plus | connected. Check wiring to |
|
or when normal source fails. | engine cranking and starting. | engine starting contacts. |
|
|
|
|
|
Transfer switch does not | Wait for Feature 2B time delay | Generator output circuit | Voltmeter should read at |
transfer the load to the | to time out. | breaker must be closed. | least 90% of nominal phase to |
emergency source after the |
| Generator frequency must be | phase voltage between |
| at least 95% of nominal (57 | transfer switch terminals EA & | |
|
| Hz for a 60 Hz system.) * | EC (or EL1 & EL2 for 2 pole)* |
|
|
|
|
Transfer switch does not | Wait for Feature 3A time delay |
| Voltmeter should read at least |
transfer the load to normal | to time out. |
| 90% of nominal phase to |
source when normal returns |
| phase voltage between | |
or when the Transfer Control |
| transfer switch terminals NB & | |
|
| ||
switch is released. |
|
| NC, NC & NA, & NA & NB (or |
|
|
| NL1 & NL2 for 2 pole). |
|
|
|
|
Wait for Feature 2E time delay | Starting control must be in the |
| |
not stop after load retransfer | to time out. | automatic position. | |
to the normal source. |
|
|
|
|
|
|
|
* These are factory settings. Refer to Controller User’s Guide.
If the problem is isolated to circuits on the controller or the transfer switch, call your local ASCO Power Technologies sales office or ASI. In the United States, call
MANUAL LOAD TRANSFER
This procedure manually transfers load to other source if the Transfer Switch or Control Panel are out of service.
! |
|
Close all enclosure doors to prevent personal |
|
injury in case of electrical system fault. |
|
1. Be sure that the Bypass Handle is in the BYPASS | Figure |
POS (position) (see page |
2.Be sure that the Isolation Handle is in the TEST or DISCONNECTED position (see page
3.Turn the Bypass Handle clockwise to AUTOMATIC POS (position).
4.Then
-Emergency Source - pull out the handle
-Normal Source - push in the handle