Emerson 400A manual Testing & Service, Preventive Maintenance, Disconnecting the Controller

Page 11

SECTION 3 TESTING & SERVICE

PREVENTIVE MAINTENANCE

For high reliability and long life for the ATS:

Operate the switch at least once a month. Perform this 4–step Electrical Operation Test (test with load transfer).

Transfer Switch Test

1.Press and hold the door-mounted Transfer Test button until the engine starts and runs. This should happen within 15 seconds.

2.The transfer switch will operate to the Emergency position. If the Transfer To Emergency Delay is used, the transfer will occur after a time delay (up to 5 minutes). For immediate transfer press Bypass Time Delay button.

3.The Transfer Switch will operate back to the Normal position after the Retransfer To Normal Delay (up to 30 minutes). For immediate retransfer press Bypass Time Delay button.

4.Unloaded Running (Engine Cooldown) Delay allows engine to run unloaded for 5 minutes.

Checklist for Yearly Inspection

Hazardous voltage capable of causing shock, burns, or death is used in this switch. Deenergize both Normal & Emergency power sources before performing inspections!

SClean the enclosure. De–energize all sources, then brush and vacuum away any excessive dust accumulation. Remove moisture with a clean cloth.

SCheck the transfer switch contacts. De-energize all sources, then remove the transfer switch barriers and check contact condition. Replace the contacts if they become pitted or worn excessively. Reinstall the barriers carefully.

SMaintain transfer switch lubrication. Under normal operating conditions no further lubricating is required. Renew factory lubrication if the switch is subjected to severe dust or abnormal operating conditions or if TS coil is replaced. Order lubricant 625550–001(Castrol EndurexR 4000 lubricant).

SCheck all cable connections & retighten them. Torque to values shown on transfer switch label.

Replacement parts. When ordering parts provide the Serial and Catalog Nos. from the transfer switch nameplate. Contact ASI. In the US call 1–800–800–ASCO (2726)).

DISCONNECTING THE CONTROLLER

The harness disconnect plugs are furnished for repair purposes only and should not have to be unplugged. If the controller must be isolated, follow these steps carefully.

Disconnecting the Plugs

1.Observe the position of the transfer switch.

a.If the transfer switch is in the Normal position, place standby engine starting control in the off position. Then open the emergency source circuit breaker.

b.If the transfer switch is in the Emergency position, open the normal source circuit breaker. Place the engine starting control in the test or run position.

2.Separate the quick disconnect plugs by squeezing the latches. Do not pull on the harness wires.

3.Label, remove, and tape the signal wires connected to the engine start terminals on the transfer switch: TB1 and TB3, or TB1 and TB2.

Reconnecting the Plugs

1.Observe the position of the transfer switch.

a.If the transfer switch is in the Normal position, be sure that the standby engine starting control is still in the off position. The emergency source circuit breaker still should be open.

b.If the transfer switch is in the Emergency position, normal source circuit breaker still should be open.

2.Reconnect the signal wires connected to the appropriate engine start terminals on the transfer switch. See Section 1, Engine Starting Contacts.

3.The harness plugs and sockets are keyed. Carefully align the plugs with the sockets and press straight in until both latches click.

4.Restore the opposite source as follows:

a.If the transfer switch is in the Normal position, place the standby engine starting control in the automatic position. Then close the emergency source circuit breaker.

b.If the transfer switch is in the Emergency position, close the normal source circuit breaker. The load will be automatically retransferred to the normal source after the Retransfer to Normal Delay. For immediate retransfer, press Bypass Time Delay button. Place the engine starting control in the automatic position.

3---1

Image 11
Contents Rating Label Operator’s ManualPage 300 400 Nameplate and Catalog Number IdentificationPage Installation Controller Ground Engine Starting ContactsHarnesses Auxiliary CircuitsManual Operation Test Installation Functional TestVoltage Checks InstallationElectrical Operation Retransfer to Normal Sequence of OperationTransfer To Emergency Disconnecting the Controller Testing & ServicePreventive Maintenance Manual Load Transfer Testing & ServiceTROUBLE-SHOOTING Trouble-Shooting the Motor Load Transfer Feature refer toTime Delay Settings AdjustmentsTime Delay Adjustment Sensor AdjustmentsSW3 actuator On each DIP switch Off on AdjustmentsHow to Change a Setting SwitchesBUILT-IN Engine Exerciser Control Features Engine ExercisersDIP Switch Settings How to Set Built-In TimerProgrammable Engine Exerciser Module Control FeaturesRun Time Display Daylight Savings Time Adjust DisplayFast / Slow Adjust Display Fill in your settings for future referenceLoad Disconnect Feature Remote Control FeaturesInphase Monitor For Motor Load Transfer Controls Control Features Optional Strip Heater AccessoryStrip Heater Accessory Available KitsIndex