Functional Test

The Functional Test consists of three checks: manual operation, voltage checks, and electrical operation.

NOTICE

Do these checks in the order presented to avoid damaging the automatic transfer switch.

Read all instructions on the Wiring Diagram and labels affixed to the automatic transfer switch. Note the control features that are provided and review their operation before proceeding.

1 – Manual Operation Test

A detachable manual operator handle is provided on the Transfer Switch for maintenance purposes only. Manual operation of the transfer switch should be checked before it is energized (operated electrically).

 

maintenance

hole

handle

 

shaft

 

Figure 1-4. Removable maintenance handle on

260 and 400 ampere transfer switches.

Do not manually operate the transfer switch until both power sources are disconnected: open both circuit breakers.

1.Insert the maintenance handle into the hole in the shaft, left side of the operator.

2.Move the maintenance handle as shown to manually operate the transfer switch. The switch should operate smoothly without any binding. If it does not, check for shipping damage or construction debris.

3.Return the transfer switch to the N (normal) position.

4.Remove the maintenance handle and store it on the transfer switch in the place provided.

NOTICE

Verify that the maintenance handle has been removed before proceeding!

Now continue to 2 – Voltage Checks on next page.

1---3

Image 7
Contents Rating Label Operator’s ManualPage 300 400 Nameplate and Catalog Number IdentificationPage Installation Controller Ground Engine Starting ContactsHarnesses Auxiliary CircuitsManual Operation Test Installation Functional TestVoltage Checks InstallationElectrical Operation Transfer To Emergency Sequence of OperationRetransfer to Normal Preventive Maintenance Testing & ServiceDisconnecting the Controller Manual Load Transfer Testing & ServiceTROUBLE-SHOOTING Trouble-Shooting the Motor Load Transfer Feature refer toTime Delay Settings AdjustmentsTime Delay Adjustment Sensor AdjustmentsSW3 actuator On each DIP switch Off on AdjustmentsHow to Change a Setting SwitchesBUILT-IN Engine Exerciser Control Features Engine ExercisersDIP Switch Settings How to Set Built-In TimerProgrammable Engine Exerciser Module Control FeaturesRun Time Display Daylight Savings Time Adjust DisplayFast / Slow Adjust Display Fill in your settings for future referenceInphase Monitor For Motor Load Transfer Remote Control FeaturesLoad Disconnect Feature Controls Control Features Optional Strip Heater AccessoryStrip Heater Accessory Available KitsIndex