When determining where to install the switch, verify that these guidelines are met:

Airflow around the switch and through the vents is unrestricted.

Temperature around the switch does not exceed 113°F (45°C).

Humidity around the switch does not exceed 85 percent.

Altitude at the installation site is not greater than 10,000 feet.

Clearance to the switch front and rear panels meets these conditions:

Front-panel LEDs can be easily read.

Access to ports is sufficient for unrestricted cabling.

AC power cord can reach from the

AC power outlet to the connector on the switch rear panel.

Access to the rear of the rack is sufficient for connecting StackWise cables to stacked switches.

Cabling is away from sources of electrical noise, such as radios, power lines, and fluorescent lighting fixtures.

For 10/100/1000 ports, the cable length from a switch to an attached device cannot exceed 328 feet (100 meters).

For cable lengths for small form-factor pluggable (SFP) modules, see the documentation that shipped with the module.

26

Image 26
Contents Including License and Warranty About this Guide Taking Out What You NeedShipping Box Contents Running Express Setup Equipment that You Supply to Run Express SetupMode button Page Page Page Refreshing the PC IP Address Managing the SwitchUsing the Device Manager Downloading Cisco Network AssistantCommand-Line Interface Other Management OptionsPreparing the Wireless LAN Controller for Operation Using the Configuration Wizard to Configure the ControllerUnder Contents, click Controller Device Manager Page Page Click Next. The Miscellaneous Configuration page appears Page Page Page Page Click Save and Reboot Logging into the ControllerVerifying Interface Settings and Port Operation Connecting Access Points Planning Switch Stacks Powering ConsiderationsCabling Considerations Vertical StackingRack-Mounting Equipment That You SupplyBefore You Begin Installation Warning Statements Page Attaching the Brackets Front-mounting positionRack-Mount the Switch Connect the StackWise Cables Connect to the Switch Ports Connect to 10/100/1000 PortsInstall the SFP Modules and Connect to the Ports Troubleshooting Express Setup Case of DifficultyResetting the Switch Troubleshooting the Wireless Controller Accessing Help OnlineObtaining Documentation For More InformationCisco.com Product Documentation DVD Ordering DocumentationDocumentation Feedback Cisco Product Security OverviewReporting Security Problems in Cisco Products Obtaining Technical AssistanceSubmitting a Service Request Cisco Technical Support & Documentation WebsiteDefinitions of Service Request Severity Obtaining Additional Publications and InformationPage Cisco Limited Lifetime Hardware Warranty Terms Duration of Hardware Warranty Page Page USA