Compaq 3000 manual Attaching the Mounting Bracket Slide Assembly to the Rack

Page 48

3-14Rack-Mount Server Installation

Attaching the Mounting Bracket

Slide Assembly to the Rack

WARNING: To reduce the risk of personal injury or damage to the equipment, be sure that the rack leveling feet are extended to the floor and support the full weight of the rack. Each rack must be level and stable. Racks that are not coupled together require the installation of stabilizers. This must be done before you perform any work on the rack.

See the Rack Planning and Installation Guide for more information on leveling feet and stabilizers.

Measuring with the Template

The template provided with the server offers an easy and reliable way to properly position the server in the rack. Use the tabs on the template to suspend it from the lower hole of a two-hole set of perforations in the vertical side rails. Pencil mark the attachment points for the mounting bracket assemblies, the cage nuts for the face-plate thumbscrews, and the top of the server. Use the tick marks on the rack side rails to insure level installation of the server. See illustrations and instructions printed on the template.

IMPORTANT: Determine the server's place in the rack before you start installing the mounting bracket assemblies. To remind you of the proper placement of the server in the rack, refer to the Rack Builder report you printed when you planned your rack configuration. Always mount the heaviest item on the bottom of the rack and work from the bottom to the top.

1.Starting at the bottom of the rack, or at the top of a previously mounted component, measure the screw hole locations for the server's mounting bracket assemblies. Pencil mark the locations on the outside of the rack. Do this on both the front and the back of the rack.

Image 48
Contents ProLiant Compaq ProLiant 3000 Setup and Installation Guide Contents Installation Overview Iv About This GuideInstalling Hardware Options Integrated Management Vi About This GuideAppendix C ViiAbout This Guide How this Manual is OrganizedViii About This Guide Text Conventions KeysSymbols in Text Product Safety InformationSymbols on Equipment About This GuideProLiant 3000 Setup and Installation Guide Getting Help Compaq CDsCompaq Systems Reference Library CD Compaq SmartStart and Support Software CDOther Hardcopy Documents Compaq Web SiteCompaq Management CD XiiiTelephone Numbers Xiv About This GuideFinland 9800-206-720 90-6155-9899 Xvi About This Guide Compaq ProLiant 3000 Server Features Standard FeaturesProcessor Boards 2Compaq ProLiant 3000 Server Features Cache Memory and System ArchitectureSystem Memory Expansion SlotsMedia Bays KeyboardVideo High-Availability Features 4Compaq ProLiant 3000 Server FeaturesSystem Management Power Supply WarrantyFans Management and Configuration Tools 6Compaq ProLiant 3000 Server FeaturesSmartStart Disk Drive Fault Tolerance Compaq Insight ManagerSecurity Features Automatic Server Recovery-2 ASR28Compaq ProLiant 3000 Server Features Compaq Integrated Remote Console Compaq Integrated Management DisplaySupported Drive Configurations 10Compaq ProLiant 3000 Server FeaturesInterlock Switches Installation Overview Server Warnings and Precautions 2Installation OverviewPre-installation Planning Power RequirementsServer Temperature Requirements 4Installation OverviewGrounding Installation Procedure Installing a Rack Mount ModelInstalling a Tower Model 6Installation OverviewProLiant 3000 Setup and Installation Guide Rack-Mount Server Installation Rack Warnings and Precautions2Rack-Mount Server Installation Rack Temperature Requirements Rack Internal Temperature Maximums4Rack-Mount Server Installation Airflow RequirementsUnpacking the Server Locating Materials and Documentation6Rack-Mount Server Installation ProLiant 3000 Setup and Installation Guide 8Rack-Mount Server Installation Preparing the Mounting Brackets Slide Rail AssembliesAttaching the Bracket Rail to the Mounting Bracket 10Rack-Mount Server Installation Removing the component rail from the bracket railProLiant 3000 Setup and Installation Guide 12Rack-Mount Server Installation Attaching the bracket rail to the mounting bracket Attaching the Mounting Bracket Slide Assembly to the Rack 14Rack-Mount Server InstallationMeasuring with the Template ProLiant 3000 Setup and Installation Guide 16Rack-Mount Server Installation Inserting Cage Nuts in the Rack FrameAttaching the Mounting Bracket Assembly to the Rack Inserting cage nuts18Rack-Mount Server Installation Important Use only the bottom hole of the bracket as shown11.Cage nut and back of mounting bracket assembly installed 20Rack-Mount Server Installation Attaching Component Rails to the ServerAttaching the Cable Management Arm Bracket 13.Attaching a cable management arm bracket to the server22Rack-Mount Server Installation Loading the Rack Server14.Loading the rack server 24Rack-Mount Server Installation Attaching the Cable Management ArmProLiant 3000 Setup and Installation Guide 26Rack-Mount Server Installation Attaching the Optional Cable SupportOptional Installation Service 17.Attaching the cable support to the rackInstalling Hardware Options Accessing Non Hot-Plug Areas Accessing Processors, Memory Board, System Board2Installing Hardware Options ProLiant 3000 Setup and Installation Guide Accessing the Processor 4Installing Hardware OptionsRemoving the terminator board Accessing Other System Board Components 6Installing Hardware OptionsSystem Board Switches Accessing Dimm Sockets on the Memory Board8Installing Hardware Options Removing the memory boardInstalling memory board Memory Banks10Installing Hardware Options Memory banks on the system board J12 J11 J10 BankAccessing the Drive Cage Back Plane 12Installing Hardware Options 10.Removing a fan11.Removing the front panel 14Installing Hardware Options 12.Partially pull out the drive cageInstalling the Duplex Enable Board Option 14.Removing the simplex enable board16Installing Hardware Options 15.Installing the duplex enable board16.Re-installing the drive cage 18Installing Hardware Options 17.Connectors on back of drive cageReplacing the Side Access Panel 18.Example cable connection to Scsi controller20Installing Hardware Options Interlock SystemAccessing Dimm Sockets on System Board 19.Removing the side panel22Installing Hardware Options 20.Installing system board Dimm banksAccessing Hot-Plug Areas Accessing the Hot-Plug Scsi Drives24Installing Hardware Options Scsi ID Numbers 26Installing Hardware Options Or Channel BPre-Failure Warranty Insight Manager AlertServer Configuration Utilities Configuring the Server with SmartStart2Server Configuration and Utilities Inserting the CD-ROMUsing the System Configuration Utility 4Server Configuration and Utilities Resolving Resource ConflictsStarting the System Configuration Utility System Configuration Utility Main Menu System Configuration Menu6Server Configuration and Utilities Configuring Hardware Add or Remove Boards8Server Configuration and Utilities System PartitionCreating a New System Partition 10Server Configuration and Utilities Verifying the System PartitionUpgrading the System Partition Configuration Backup Configuration Backup Configuration History FilesSystem Configuration History Log Files 12Server Configuration and UtilitiesConfiguring PCI Boards Automatically Installing an Operating SystemRemoving Boards 14Server Configuration and Utilities SMP Operating System SupportManual installation Loading Compaq Device DriversNovell NetWare Device Drivers form Compaq 16Server Configuration and Utilities Microsoft Windows NT Device Drivers from CompaqSCO OpenServer and SCO UnixWare Device Drivers from Compaq 18Server Configuration and Utilities IBM OS/2 Device Drivers from CompaqBanyan Vines Device Drivers from Compaq Diagnostics and Other Utilities 20Server Configuration and UtilitiesIntegrated Management Integrated Management DisplayNormal Run-time Behavior 2Integrated Management Idle Screen TextNavigation Buttons Integrated Management Display buttonsDisplay Symbols Integrated Management Display Symbols4Integrated Management System Behavior with Error Events AlertMenu Structure 6Integrated ManagementIntegrated Management Log Multiple Ways of Viewing the Log Compaq Insight Manager8Integrated Management Viewing the Event List Compaq Survey Utility Compaq IML Management Utility10Integrated Management List of Events END of EventEvent Messages 12Integrated ManagementEvent Type Event Message Post Error Power Cord Set Requirements General RequirementsTable A-1 Power Cord Set Requirements By Country 2Power Cord Set RequirementsCountry-Specific Requirements Regulatory Compliance Notices Federal Communications Commission NoticeClass a Equipment Class B Equipment2Regulatory Compliance Notices Modifications CablesCanadian NoticeAvis Canadien European Union Notice4Regulatory Compliance Notices Japanese Notice Australian Notice Laser Safety Warnings Laser DevicesCompliance with Cdrh Regulations Compliance with International RegulationsLaser Product Label Laser InformationBattery Replacement Notice 8Regulatory Compliance NoticesInternal CD-ROM Drive Table C-1Internal CD-ROM Index Index-1Index Index-3 Scsi Index-5