American Power Conversion Automatic Disconnect Switch user manual Operation, Start Up

Page 11

Operation

Start Up

Primary/Secondary Access Panel

To remove the access panel covering the Primary/Secondary Select button remove the screw that secures the panel to the enclosure. Slide the access panel slightly to the right and then pull the access panel toward you.

Operation

Indicators and Controls

Local Power Remote Power

Reset/Test

Local 63V Fault

Primary/

Secondary

Select

Primary

Secondary

220V Normal

Circuit Breaker

Local Power

Remote Power

Reset/Test

Local 63V Fault

Primary

Secondary

220V Normal

Circuit Breaker: The circuit breaker protects the 220 V input from overload conditions.

Local Power: Green LED indicates that the Automatic Disconnect Switch is providing power to the cable system.

Remote Power: Green LED indicates the cable system is receiving power from a source other than the Automatic Disconnect Switch.

Broadband Automatic Disconnect Switch User Manual

11

Image 11
Contents Broadband Automatic Disconnect Switch Page About this unit SafetySpecifications IntroductionUnpack InstallationSchematic Overview of the Automatic Disconnect Switch System Utility Power Connections Mount the Automatic Disconnect Switch on the WallHardwire the Automatic Disconnect Switch Cable System Connections Connector InstallationCoax Connection   Cable Modem Connection Start Up Indicators and ControlsPrimary/Secondary Access Panel OperationSecondary Status Cable ModemPrimary Status Problem and/or Possible Cause Solution Limited WarrantyFCC Compliance Notice Service