After installing the drive, follow the sequence outlined below for initial startup.

1.Place the on/standby switch in the on ( l ) position. What follows depends on the setting of the Start Command option and the Spinup Delay option jumpers on the control board.

If the Start Command option jumper was connected, the spindle spinup begins immediately after a Start Unit command is received from the SCSI bus.

If the Spinup Delay option jumper and the Start Command option jumper were both disconnected, the spindle spinup begins immediately.

If the Spinup Delay option jumper was connected and the Start Command option jumper was disconnected, the spindle spinup begins after a se- quence delay interval. The length of this interval equals the SCSI Bus ID number (Target ID) multiplied by 10 seconds.

For example:

SCSI bus ID 0 = 0 second delay

SCSI bus ID 7 = 70 second delay

2.Observe that the Ready LED begins flashing when power is applied to the spindle motor. The Ready LED is one of two green control board LEDs—see Figure 16.

3.Observe that the Ready LED lights steadily within 30 seconds after the power is applied to the spindle motor. This indicates that drive motor is up to speed and that heads are at track 0.

4.Observe that the Heartbeat LED is blinking. This indicates that the SCSI controller is operating properly. The Heartbeat LED is the other green control board LED—see Figure 16.

If all of these events occurred, the drive is now ready for online operation. If any event did not occur, a problem exists in the drive or its installation—refer to section 5.

Image 37
Contents Elite Disc Drive ST43400N/ND Contents Electrostatic discharge protection PrefaceImportant safety information and precautions ST43400N/ND User’s Manual SeaFAX 408 Technical support servicesSeaFONE 408 SeaBOARDST43400N/ND disc drive General descriptionSize Dimensions Characteristics Conditions Specifications Page Drive functional block diagram Site requirements InstallationEnvironmental requirements Airflow requirements Suggested airflow Mounting orientations Space requirementsDimensions of the drive and power supply Power requirements Interface requirements Grounding requirementsScsi Unshielded single-ended I/O cabling Signal Name Pin Number Unshielded differential I/O cabling Signal Name Pin Number Unpacking Unpacking, inspection, and repackingInspection RepackingSetting the control board jumpers Installation proceduresJ4A Installing the power supply Power supply installation Installing an optional bezel Attaching a bezel Mounting the drive Mounting the drive O cable attachment Connecting the system I/O cablingTerminator attachment-single-ended I/O Terminator attachment-differential I/O Grounding the system Synchronizing the spindle System diagram for spindle syncJ4A Installation Verification Operation Switches and indicatorsSwitches and indicators Switch or Indicator Function Operating instructions Parts data Options and accessories Part Number Description Observing maintenance precautions MaintenanceRemoving and replacing a drive Arranging for depot repairPacking a drive for shipment Removing and replacing a power supplyPage Maintenance Publication Number 83327630, Rev. a