GE Power Supply Recycling the UPS at the end of service life, Battery replacement procedure 3kVA

Page 19

g

Digital EnergyGT Series

6.3.2Battery replacement procedure) 1.5kVA 1 Remove front panel

2 Unscrew two bolts of the

3 battery terminal cover and remove it

4 Unplug battery connectors

5 Unscrew five bolts of the

6 battery compartment cover and remove it

7 Unscrew two bolts of battery fixer and remove it

8 Pull out the battery set and renew it

9 Assemble UPS

by reverse procedure.

Fig. 6.2

6.3.3Battery replacement procedure) 3kVA

NOTE: The battery banks should be installed by service personnel.

1Remove front panel

2Unscrew two bolts of the battery compartment

3Remove battery cover

4Unscrew two bolts

5/6 Remove stop holder and battery terminal 7 Grasp the tag to pull out the battery sets.

Be careful, heavy weight! Notice not to let the battery set to drop in accident

7When you see the first warning label, please disconnect all leads

Continue horizontally pulling the battery set 1 until you see the next warning label (See fig. 6-4)

7a Now you can easily release battery set 1! (Gently lift it up!) Put battery set 1 beside.

7b Continue pulling out battery set 2.

8Unplug all connectors of batteries

9Renew the batteries and re-install them with reverse procedure.

Fig. 6.3

Fig. 6.4

6.4Recycling the UPS at the end of service life

GE Digital Energy, in compliance with environment protection recommends that the UPS equipment, at the end of its service life, must be recycled conforming to the local applicable regulations.

OPM_GTU_19X_1K0_3K0_XUS_V014

18

GT-UL Series: User manual 1.2 (US)

Image 19
Contents Digital EnergyTMGT Series Digital Energy GT Series Important Safety Instructions Installation Important Safety InstructionsGeneral Transport/storage Batteries1kVA Model Fccis Interference StatementsRear panel InstallationPackage contents LocationMounting in a 19 enclosure Vertical installationConnecting the load Connecting an external battery packUL 1778 safety requirement Connecting the RS232/dry contact interfaceChecking the site-wiring fault LED Connecting to the utility power supply 1000/1500VA2200/3000VA Operation Panel OperationUse Normal Operation Start-upUse Abnormal Conditions Bypass operation Replace batteryShort circuit Description CommunicationDry Contact RS232Snmp Plug-in Card optional SpecificationsFunctions Maintenance Optional FeaturesBattery replacement procedure 1.5kVA 1 Remove front panel Recycling the UPS at the end of service lifeBattery replacement procedure 3kVA Problem Possible Cause Solution TroubleshootingGT Model 1000R UL 1500R UL 2200R UL 3000R UL Specifications