9.Slide the cover end of the new Tape Drive under the servers top cover and tighten all four 94) thumb screws.

10.Restore all power cables to their power source.

.Power up the server and test the new Tape Drive.

SV-2000-X2 Server (CENTRIX / JHSV)

 

Part Number: 1008080

Page 60 of 82

Version 1.4. 01/12/2010

 

Image 60
Contents SV-2000-X2 Server Centrix / Jhsv Operations Manual Copyright 2008 Technology Advancement Group, Inc TAG TrademarksAbout TAG Summary of QualificationsCore Competences Engineering Manufacturing and IntegrationLifecycle Management About TAG Summary of Qualifications Core CompetenciesPage Date Version Number Updated By Description Document Revision HistoryAbout This Manual Scope and AudienceOrganization Table of Contents RAID List of Figures 1SV-2000-X2 Front View11 Stripe Size Chapter Safety Instructions Types of warnings used in this manualPage SV-2000-X2 2U Server Server Overview Product InformationSpecifications Chassis & power supply Motherboard and On-board FeaturesSV-2000-X2 Server Fan Controller Processor & CacheAdditional specifications 3 SV-2000-X2 Server Highlights4 SV-2000-X2 Server Server ComponentsMotherboard Model and Type Power Management Identifying your I/O ConnectorsSystem Memory Identifying System MemoryStandard Server Components Floppy DrivesScsi HP 920 LTO-3 Ultrium tape drive 5Internal Tape Drive 3 D/DVD DriveDual-redundant, auto-sensing power supply Input Power Line FrequencyPower Connector 7Hot-Swap Power Supply PCI I/O Expansion Cards Adaptec 5805 SAS/SATA RAID ControllerAdaptec 29320 ALP-R Scsi Controller 9Adaptec 29320 ALP-R Scsi ControllerProcedures Procedures Identifying Server Components Using Device ManagerServer Startup Server Shutdown1Control Panel Double-click the System icon. Figure Page Working with Device Properties 4Device ManagerPage Installing and Removing Hardware in Windows Using the Add New Hardware Wizard6Control Panel Double-click the Add Hardware icon. Figure Installing Legacy Peripherals Removing Legacy Peripherals9System Properties Click the Hardware tab 10Device Manger TAG Approved Bios Common Bios SettingsHard Drives Boot Sector Virus Boot SequencePasswords MemoryPlug and Play Bios Bios Configuration for SV-2000-X2 12Load Optimized Defaults 13Enhanced Intel 14Enhanced Intel, Disable 15Processor Confirmation Screen 16Deep C-state Support Screen 17USB Configuration 18Intel Virtualization Technology 19Save and Reset 20Grounding Wrist Strap Replacing a Hot-Swap Power Supply Module Replacing a Hot-Swap Hard Drive 11.1 146GB SAS Hard Drive Removing the Server CoverInstall system memory Unlatch both Dimm socket levers, as shown in FigureReplacing the Cmos Battery Install Tape Drive Ultrium 920 Tape DriveRemove Tape Drive Page RAID RAID RAID DefinedRAID Level 1Array Configuration Create a RAID 5 Array On AdaptecPage Initialized 6Create Array 7Select Drives Page Page Page Page Page 13Cache Functionality 14Write Caching Page Operations Manual Press Enter to continue. Figure 17Cache Warning 18Hot Spare Check 19 Exit Utility About RAID Global and Hot Spares Global and Dedicated Hot SparesContact