2.Determine the number and configuration of Lamp Modules and Power Junction Modules. Note: the maximum number of Lamp Modules (19-1000) to be installed per Power Junction Module (19-1020) is 24.

3.Mark the location of the lower mounting bracket on the lower mounting surface of the installation area.

4.Measure overall length/height required for the installation (Figure 2a, dimension ‘A’). This dimension is the distance from the lower mounting surface to the upper mounting surface of the mounting location. Record the measurement in the table in Figure 2a. for Dimension A.

5.Referencing Dimension A, deduct ½” from the overall distance from the lower to upper mounting surface and record as Dimension B. This is the overall length of the Main Support.

6.Install the lower bracket to the lower mounting surface of the installation area in the previously marked location. Four sheet metal screws (provided) should be used to securely fasten the lower bracket to the lower mounting surface (see Figure 2a).

7.Place the Main Support on a horizontal surface in an appropriate work area. Measure and mark off the Dimension B onto the Main Support (see Figure 2b). Then make one cut through the cross-section of the Main Support using a tool appropriate for cutting aluminum. Cut only from one end, as it is important to retain a wiring feed-through hole in the Main Support section to be installed.

Figure 2b

INSTALLATION OF THE LAMP MODULES

1.Carry the Main Support into the installation area. Place the upper mounting bracket onto the top end of the Main Support. Do not install screws in the upper mounting bracket at this time.

2.Place the lower end of the Main Support into the lower mounting bracket, which is secured to the lower mounting surface.

3.Swing the Main Support into place so that it is vertical.

4.When vertical, use the supplied hardware to anchor the upper mounting bracket into the duct ceiling.

5.First mark the location where the Power Junction Module is to be attached. It is important to mount the Power Junction Module near, but not covering, the wire feed through hole in the Main Support. It is recommended that the Power Junction Module be attached to the upper end of the Main Support.

6.Mark the Main Support locations where the Lamp Modules should be attached.

Note: the maximum number of Lamp Modules (19-1000) to be installed per Power Junction Module (19-1020) is 24.

7.Once the desired locations for the Lamp Modules and Power Junction Modules have been identified, disassemble the upper mounting bracket from the upper mounting surface and return the Main Support to the work area.

19-2021 Rev E, 06/05/07

6

Image 6
Contents Flex Table of Contents Temperature Ratings Specifications Power Ratings Power ConsumptionInstallation ApplicationProduct Registration Dimension a Dimension B Dimension C Mounting LocationInstallation of the Lamp Modules Rev E, 06/05/07 Installation of the Power Junction Module Preparation of the WIRE/RACEWAY CoverRaceway Installation of Main Support Into AIR Handling Duct Lamp Installation Electrical Connection of the SystemRev E, 06/05/07 Rev E, 06/05/07 Operation Troubleshooting and Service Broken Lamp Clean-upMercury Notice Cleaning the Lamps Replacing the Lamp AnnuallyRev E, 06/05/07 Equipment Warranty Pureuvc661 257-4698 fax