NEC 2400 ipx system manual Test of OPE lamp on Iptrk circuit card

Page 56

OPERATION TESTS AFTER INSTALLATION

3.FCCS NETWORKING VIA IP [F-36]

When using the IPTRK circuit card for FCCS Networking via IP [F-36] (Point-to- Multipoint Connection), perform the following circuit card operation tests. If necessary, perform fault repairs.

ATTENTION

Contents Static Sensitive

Caution:Some LSIs on this circuit card may be hot. Handle with care.

1.Test of OPE lamp on IPTRK circuit card:

Handling Precautions Required

a.) See if the OPE lamp on the IPTRK circuit card is lighting green. This lamp will light if the circuit card is operating normally.

b.) When the OPE lamp is OFF, initialize the circuit card, or perform the insertion/extraction of the circuit card once or twice. If the lamp still does not light, replace the circuit card.

2.Test of SUBOPE0 and SUBOPE1 lamps on IPTRK circuit card:

a.) See if the SUBOPE0 and SUBOPE1 lamps on the IPTRK circuit card are lighting green. Note that SUBOPE1 should light if the circuit card is furnished with an optional sub board (PZ- 8VCTB).

b.) When either (or both) of the lamps are OFF, initialize the circuit card, or perform the insertion/ extraction of the circuit card once or twice. Also, if a sub board is in use, make sure the daughter board is securely attached to the IPTRK circuit card (main board). If the lamp still does not light, replace the circuit card.

IP-LRR

Is IP network available for connection?

IP-LINK

Is IPTRK-IP network link physically established?

F-LRR

Is FCCS network available for connection?

F-LINK

Is IPTRK-FCCS network link physically established?

Not Used

MB

MBR

BUSY SUBOPE3 SUBOPE2

L3

L2

L1

IP-COL

F-COL

Not Used

MODE

IP-TXRX

IP-100M

IPCON

F-TXRX

F-100M

FCON

OPE

Is IPTRK card operating normally?

SUBOPE1

Is CPU of sub board operating normally?

SUBOPE0

Is CPU of IPTRK card’s main board operating normally?

L1

Is FCCS network link established?

Sub Board (PZ-8VCTB)

IPTRK Circuit Card

Figure 4-2 Lamps to be Tested (FCCS Networking via IP [F-36] [Point-to-Multipoint Connection])

NDA-24318CHAPTER 4

Page 49

Issue 1

Image 56
Contents Issue NovemberLiability Disclaimer NEAX2400 IPX Table of Contents NEAX2400 IPXList of Figures List of Tables This page is for your notes Introduction GeneralService Features to be Provided NEAX2400 IPXBlock Diagram Ccis Networking via IP To Iptrk Block Diagram Fccs Networking via IP HOW to Follow this Manual and Related Reference Manuals Circuit Card ExplanationsCircuit Card Explanations PA-8IPTB Circuit Card Mounting Locations Port Assignment for PA-8IPTB Circuit Card Lamp indication meanings are shown below Meaning of each switch on this card is shown below OFF SW20 Dynamic Controlling PAD no Pattern Send Receive PA-8IPTB Attachment of Sub Board PZ-8VCTB onto Iptrk Circuit Card PZ-8VCTB Sub Board Office Data Programming Ccis Networking VIA IP C-163Required Hardware Required Hardware Point-to-Multipoint Connection Service Conditions Feature Feature Name Condition Number Data Programming Port Assignment of Bch for Ccis Tie Line Acsc Iptrk Ccis Node Node B Node C Fccs Networking VIA IP F-36 Overview of Fccs Networking via IP F-36Example Required Hardware for Fccs Networking via IP F-36 Node a Node B Alternate Routing OK Symbols Bch Speech Iptrk firmware ASYDL, SYS 1, Index 527, b6 Example Data Assignment Acrd 10 Example Data Assignment Actk Fchn = 1 Fchen = 12 Example Assignment of Destination IP and Next IP Aeth Step Iptrk Fccs Data Assignment at Node a Fccs Routing Example Data Sheets 16 Fccs Networking via IP F-36 Example Data Sheet NEAX2400 IPX FPC DTI FCH Fchn Fchn FPC=3, FCHN=3, CRT=70, DSTIP=0.0.0.0, NEXTIP=0.0.0.0 Note Operation Tests After Installation Ccis Networking VIA IP C-163/VOICE Over IP H.323Contents Test of OPE lamp on Iptrk circuit card Fccs Failure