Wiring and Connecting the UPS
5000/6000 VA XLI MODELS ONLY: HARDWIRING INSTRUCTIONS
•Wiring must be performed by a qualified electrician.
•Install a high magnetic 30/32 A utility circuit breaker.
•Adhere to all national and local electrical codes.
•Use #10 AWG gauge (5 mm2) wire.
1.Switch the utility circuit breaker OFF.
2.Remove the input access panel.
3.Remove circular knockout.
4.Run #10 AWG gauge (5 mm2) wire through the access panel, and connect the wires to the terminal block (green: ground, brown: hot, blue: neutral). Use an appropriate strain relief (not included).
5.Switch the utility circuit breaker ON.
6.Check line voltages.
7.Replace the access panel.
2