D. FRESH AIR SUPPLY REQUIREMENTS

The air supply (make-up air) must be given careful consideration to assure proper performance of each dryer. An unrestricted source of air is necessary for each dryer. As a general rule, an unrestricted air entrance from the outdoors (atmosphere) of a minimum of 1-1/2 square feet (0.14 square meters) is required for each dryer. If registers or louvers are installed over the openings, then the area must be increased. It is not necessary to have a separate make-up air opening for each dryer. Common make-up air openings are acceptable. However, they must be set up in such a manner that the make-up air is distributed equally to the dryers. The dryer must be installed with provisions for adequate combustion and make-up air supply.

EXAMPLE: For a bank of eight (8) dryers, two (2) unrestricted openings measuring 2 feet by 3 feet (6 square feet [0.61 meters by 0.91 meters] [0.55 square meters]) are acceptable.

IMPORTANT: Make-up air openings should not be located in an area directly near where exhaust vents exit the building.

Allowances must be made for remote or constricting passageways or where dryers are located at excessive altitudes or predominantly low pressure areas.

IMPORTANT: Make-up air must be provided from a source free of dry cleaning solvent fumes. Make-up air that is contaminated by dry cleaning solvent fumes will result in irreparable damage to the motors and other dryer components.

NOTE: Component failure due to dry cleaning solvent fumes will VOID THE WARRANTY.

10

Image 14
Contents MDG30PCC Retain This Manual In a Safe Place For Future Reference Foryour Safety Page Table of Contents Section Procedure for Functional Check of Replacement Safety Precautions SectionPage Specifications FXPSpecifications GAS only Installation Procedures Unpacking and Setting UPLocation Requirements Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements Single Dryer Venting Vertical Venting Multiple Dryer Common Venting Illus. D Importantventingreminders Electrical Information Electrical Requirements75,&$/659,&63&,,&$7,2163555 Odfn 3RVLWLYH KLWHRU5HG Uhhq UrxqgGAS Information 732*$6 This Pipe Size Requirement Page Preparation for Operation and START-UP Preoperational Tests Preoperational Instructions Coin Models Basket Tumbler CoatingShutdown Instructions Parts SERVICE/PARTS InformationService Warranty Warranty InformationReturning Warranty Cards Suggested Cleaning Schedule Routine MaintenanceCleaning Adjustments LubricationSectionvii Datalabel InformationSerial Number Procedure for Functional Check Replacement Components SectionviiiPage Dual Timer Manual Reset Burner HI-LIMIT InstructionsPhase 15/04