E. EXHAUST REQUIREMENTS

Exhaust ductwork should be designed and installed by a qualified professional. Improperly sized ductwork will create excessive back pressure which results in slow drying, increased use of energy, and shutdown of the burner by the airflow (sail) switch, burner hi-limit, or lint chamber hi-limit protector thermostat. The dryer must be installed with a proper exhaust duct connection to the outside.

When possible, it is suggested to provide a separate (single) exhaust duct for each dryer.

CAUTION: IMPROPERLY SIZED OR INSTALLED EXHAUST DUCTWORK CAN CREATE A POTENTIAL FIRE HAZARD.

CAUTION: DRYER MUST BE EXHAUSTED TO THE OUTDOORS.

IMPORTANT: It is recommended that exhaust or booster fans not be used in the exhaust ductwork system.

The exhaust ductwork should be laid out in such a way that the ductwork travels as directly as possible to the outdoors with as few turns as possible. The shape of the ductwork is not critical as long as the minimum cross section area is provided. Single or independent dryer venting is recommended.

It is suggested that the use of 90° turns be avoided; use 30° or 45° angles instead.

The ductwork should be smooth inside with no projections from sheet metal screws or other obstructions, which will collect lint. When adding ducts, the ducts to be added should overlap the duct to which it is connected. ALL ductwork joints must be taped to prevent moisture and lint from escaping into the building. Additionally, inspection doors should be installed at strategic points in the exhaust ductwork for periodic inspection and cleaning.

IMPORTANT: When connecting ductwork to the dryer exhaust duct, be sure that when screws are used they DO NOT restrict the operation (both opening and closing) of the damper.

NOTE: When the exhaust ductwork passes through a wall, ceiling, or roof made of combustible materials, the opening must be 2-inches (5.08 cm) larger than the duct (all the way around). The duct must be centered within this opening.

To protect the outside end of the horizontal ductwork from the weather, a 90° elbow bent downward should be installed where the exhaust exits the building. If the ductwork travels vertically up through the roof, it should be protected from the weather by using a 180° turn to point the opening downward. In either case, allow at least twice the diameter of the duct between the duct opening and the nearest obstruction (i.e., roof or ground level).

IMPORTANT: DO NOT use screens, louvers, or caps on the outside opening of the exhaust ductwork.

IMPORTANT: Exhaust back pressure measured by a manometer at the dryer exhaust duct area must be no less than 0 and must not exceed 0.3 inches (0.74 mb) of water column (W.C.).

11

Image 15
Contents MDG30PCC Retain This Manual In a Safe Place For Future Reference Foryour Safety Page Table of Contents Section Procedure for Functional Check of Replacement Section Safety PrecautionsPage FXP SpecificationsSpecifications GAS only Unpacking and Setting UP Installation ProceduresLocation Requirements Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements Single Dryer Venting Vertical Venting Multiple Dryer Common Venting Illus. D Importantventingreminders Electrical Requirements Electrical Information75,&$/659,&63&,,&$7,2163555 Uhhq Urxqg Odfn 3RVLWLYH KLWHRU5HGGAS Information 732*$6 This Pipe Size Requirement Page Preparation for Operation and START-UP Preoperational Tests Basket Tumbler Coating Preoperational Instructions Coin ModelsShutdown Instructions SERVICE/PARTS Information ServiceParts Warranty Information Returning Warranty CardsWarranty Routine Maintenance CleaningSuggested Cleaning Schedule Lubrication AdjustmentsDatalabel Information SectionviiSerial Number Sectionviii Procedure for Functional Check Replacement ComponentsPage Manual Reset Burner HI-LIMIT Instructions PhaseDual Timer 15/04