I. PREOPERATIONAL TESTS

ALL dryers are thoroughly tested and inspected before leaving the factory. However, a preoperational test should be performed before the dryer is publicly used. It is possible that adjustments have changed in transit or due to marginal location (installation) conditions.

1.Turn on electric power to the dryer.

2.Refer to the Operating Instructions for starting your particular model dryer.

3.When a gas dryer is first started (during initial start-up), it has a tendency not to ignite on the first ignition attempt. This is because the gas supply piping is filled with air, so it may take a few minutes for the air to be purged from the lines.

NOTE: During the purging period, check to be sure that ALL gas shutoff valves are open.

NOTE: Dryers are equipped with a Direct Spark Ignition (DSI) system, which has internal diagnostics. If ignition is not established after the first attempt, the heat circuit in the DSI module will lock out until it is manually reset. To reset the DSI system, open and close the main door and restart the dryer.

A gas pressure test should be taken at the gas valve pressure tap of each dryer to assure that the water column (W.C.) pressure is correct and consistent.

NOTE: Water column pressure requirements (measured at the pressure tap of the gas valve body):

Natural Gas -----------------

3.5 Inches (8.7 mb) Water Column.

Liquid Propane (L.P.) Gas ---

10.5 Inches (26.1 mb) Water Column.

IMPORTANT: There is no regulator provided in an L.P. dryer. The water column pressure must be regulated at the source (L.P. tank), or an external regulator must be added to each dryer.

4.Make a complete operational check of ALL safety related circuits:

a.Door Switches

b.Hi-Limit Thermostats

c.Cycling Thermostat

NOTE: The sail switch can be checked for proper operation by opening the lint door while heating circuit (gas burner or electric oven) is active (on). The heating unit should shut off within a few seconds. If not, make necessary adjustments to the sail switch.

5. Make a complete operational check of ALL operating controls.

25

Image 29
Contents MDG30PCC Retain This Manual In a Safe Place For Future Reference Foryour Safety Page Table of Contents Section Procedure for Functional Check of Replacement Section Safety PrecautionsPage FXP SpecificationsSpecifications GAS only Unpacking and Setting UP Installation ProceduresLocation Requirements Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements Single Dryer Venting Vertical Venting Multiple Dryer Common Venting Illus. D Importantventingreminders Electrical Requirements Electrical Information75,&$/659,&63&,,&$7,2163555 Uhhq Urxqg Odfn 3RVLWLYH KLWHRU5HGGAS Information 732*$6 This Pipe Size Requirement Page Preparation for Operation and START-UP Preoperational Tests Basket Tumbler Coating Preoperational Instructions Coin ModelsShutdown Instructions Parts SERVICE/PARTS InformationService Warranty Warranty InformationReturning Warranty Cards Suggested Cleaning Schedule Routine MaintenanceCleaning Lubrication AdjustmentsDatalabel Information SectionviiSerial Number Sectionviii Procedure for Functional Check Replacement ComponentsPage Dual Timer Manual Reset Burner HI-LIMIT InstructionsPhase 15/04