Consistent gas pressure is essential at ALL gas connections. It is recommended that a 3/4-inch (19.050

mm)pipe gas loop be installed in the supply line servicing a bank of dryers. An in-line pressure regulator must be installed in the gas supply line (header) if the (natural) gas pressure exceeds 12.0 inches (29.9 mb) of water column (W.C.) pressure.

NOTE: A water column test pressure of 3.5 inches (8.7 mb) for natural gas and 10.5 inches (26.1 mb) for liquid propane (L.P.) dryers is required at the gas valve pressure tap of each dryer for proper and safe operation.

A 1/8” N.P.T. plugged tap, accessible for a test gauge connection, must be installed in the main gas supply line immediately upstream of each dryer.

IMPORTANT: Pipe joint compounds that resist the action of natural gas and L.P. gas must be used.

IMPORTANT: Test ALL connections for leaks by brushing on a soapy water solution (liquid detergent works well).

WARNING: NEVER TEST FOR LEAKS WITH A FLAME!!!

ALL components/materials must conform to National Fuel Gas Code Specifications ANSI Z223.1-LATEST EDITION, or in Canada, CAN/CGA-B149.1-M91 (Natural Gas) or CAN/CGA-B149.2-M91 (L.P. Gas) or LATEST EDITION (for General Installation and Gas Plumbing), as well as local codes and ordinances and must be done by a qualified professional. It is important that gas pressure regulators meet applicable pressure requirements, and that gas meters be rated for the total amount of ALL the appliance BTUs being supplied.

IMPORTANT: The dryer and its individual shutoff valve must be disconnected from the gas supply piping system during any pressure testing of that system at test pressures in excess of 1/2 psig (3.5 kPa).

NOTE: The dryer must be isolated from the gas supply piping system by closing its individual manual shutoff valve during any pressure test of the gas supply system at test pressures equal to or less than 1/2 psig (3.5 kPa).

IMPORTANT: THIS GAS DRYER IS NOT PROVIDED WITH AN INTERNAL GAS SUPPLY SHUT OFF AND AN EXTERNAL GAS SUPPLY SHUT OFF MUST BE PROVIDED.

27

Image 31
Contents Installation Manual Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Reversing Timer SPIN/DWELL Adjustments Receiving and Handling Important InformationWhat to do if YOU Smell GAS Safety PrecautionsPage Specifications SPECIFICATIONS/COMPONENT IdentificationSpecifications Component Identification Page Location Requirements Installation ProceduresUNPACKING/SETTING UP Dryer Enclosure Requirements Fresh AIR Supply Requirements General Exhaust Ductwork Information Exhaust RequirementsPage Page Page Electrical Requirements Electrical Information78 Gas Page Ground SINGLE-PHASE 1Ø Electrical Connection LeadsPage Page GAS Information Type of GAS Page Page Preparation for OPERATION/START-UP Preoperational Tests Basket Tumbler Coating Selection can be made Preoperational InstructionsShutdown Instructions Service SERVICE/PARTS InformationParts Returning Warranty Cards Warranty InformationWarranty Cleaning Routine MaintenanceSuggested Cleaning Schedule Lubrication AdjustmentsOPL Dual Timer Models only Reversing Timer SPIN/DWELLADJUSTMENTSData Label Data Label InformationSerial Number OPL Sensoractivated Fire Extinguishing F.E. System F.E. System In ActionBefore YOU Start Check Local Codes and Permits InstallationTypical water supply Optional Manual Bypass System Reset Sensor Activated Fire Extinguishing S.A.F.E System SensorActivated Fire Extinguishing S.A.F.E. System Coin Sensor Activated Fire Extinguishing F.E. System Installation Typical water supply Optional Manual Bypass Disabled Sensor Activated Fire Extinguishing S.A.F.E. System Sensor Activated Fire Extinguishing S.A.F.E System Qty ADC113373 04/01/02-25 12/12/02-25