American Dryer Corp MDG30PCC installation manual Preparation for Operation and START-UP

Page 23

Consistent gas pressure is essential at ALL gas connections. It is recommended that a 3/4-inch (19.05

mm)pipe gas loop be installed in the supply line servicing a bank of dryers. An in-line pressure regulator must be installed in the gas supply line (header) if the (natural) gas pressure exceeds 12.0 inches (29.9 mb) of water column (W.C.) pressure. (Refer to the illustrations on the previous page.)

NOTE: A water column test pressure of 3.5 inches (8.7 mb) for natural gas and 10.5 inches (26.1 mb) for liquid propane (L.P.) dryers is required at the gas valve pressure tap of each dryer for proper and safe operation.

A 1/8” N.P.T. plugged tap, accessible for a test gauge connection, must be installed in the main gas supply line immediately upstream of each dryer.

IMPORTANT: Pipe joint compounds that resist the action of natural gas and L.P. gas must be used.

IMPORTANT: Test ALL connections for leaks by brushing on a soapy water solution (liquid detergent works well).

WARNING: NEVER TEST FOR LEAKS WITH A FLAME!!!

IMPORTANT: The dryer and its individual shutoff valve must be disconnected from the gas supply piping system during any pressure testing of that system at test pressures in excess of 1/2 psig (3.5 kPa).

NOTE: The dryer must be isolated from the gas supply piping system by closing its individual manual shutoff valve during any pressure test of the gas supply system at test pressures equal to or less than 1/2 psig (3.5 kPa).

H. PREPARATION FOR OPERATION AND START-UP

The following items should be checked before attempting to operate the dryer:

1.Read ALLCAUTION,” “WARNING,” and “DIRECTION” labels attached to the dryer.

2.Check incoming supply voltage to be sure that it is the same as indicated on the dryer data label.

3.Check to ensure that the dryer is connected to the type of heat or gas indicated on the dryer data label.

4.The sail switch damper assembly was installed and adjusted at the factory prior to shipping. However, each sail switch adjustment must be checked to ensure that this important safety control is functioning.

5.Check bolts, nuts, screws, terminals, and fittings for tightness.

6.Be sure that ALL gas shutoff valves are in the open position.

7.Check ALL back guard panels and service box covers have been replaced.

8.Make sure the lint coop support bracket has been removed.

9.Check the lint door to ensure that it is closed and secured in place.

113201 - 7

Maytag Co.

19

Image 23
Contents MDG30PCC Installation Manual MDG30PCC PH7 For Your Safety Page Table of Contents Section Safety PrecautionsMaytag Co 20.32 cm SpecificationsSpecifications Unpacking and Setting UP Installation ProceduresLocation Requirements Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements Single Dryer Venting Multiple Dryer Common Venting Multiple Dryer Venting Vertical Electrical Requirements Electrical InformationFor 110V Applications GAS Information Type of GAS This Pipe Size Requirement Preparation for Operation and START-UP Preoperational Tests Basket Tumbler Coating Preoperational InstructionsShutdown Instructions Parts SERVICE/PARTS InformationService Warranty Warranty InformationReturning Warranty Cards Suggested Cleaning Schedule Routine MaintenanceCleaning Lubrication AdjustmentsData Label Information Sectionviii Procedure for Functional Check Replacement ComponentsMaytag Co Dual Timer Manual Reset Burner HI-LIMIT InstructionsPhase Maytag Co 09/16/08