IMPORTANT: For extended ductwork runs, the cross section area of the ductwork can only be increased to an extent. When the ductwork approaches the maximum limits noted in this manual, a professional heating, ventilating, and air-conditioning (HVAC) firm should be consulted for proper venting information.

ALL ductwork should be smooth inside with no projections from sheet metal screws or other obstructions, which will collect lint. When adding ducts, the duct to be added should overlap the duct to which it is to be connected. ALL ductwork joints must be taped to prevent moisture and lint from escaping into the building. Inspection doors should be installed at strategic points in the exhaust ductwork for periodic inspection and cleaning of lint from the ductwork.

NOTE: When the exhaust ductwork passes through a wall, ceiling, or roof made of combustible materials, the opening must be 2-inches (5.08 cm) larger than the duct (all the way around). The duct must be centered within this opening.

Outside Ductwork Protection

To protect the outside end of the horizontal ductwork from the weather, a 90° elbow bent downward should be installed where the exhaust exits the building. If the ductwork travels vertically up through the roof, it should be protected from the weather by using a 180° turn to point the opening downward. In either case, allow at least twice the diameter of the duct between the duct opening and the nearest obstruction.

IMPORTANT: DO NOT use screens, louvers, or caps on the outside opening of the exhaust ductwork.

113394 - 8

Maytag Co.

15

Image 19
Contents MDG75PNH and MDG75MNV Installation Manual Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Procedure for Functional Check Section Safety PrecautionsMaytag Co 113394 Specifications SpecificationsSpecifications Gas Component Identification Maytag Co 113394 Location Requirements Installation ProceduresUNPACKING/SETTING UP Dryer Enclosure Requirements Fresh AIR Supply Requirements General Exhaust Ductwork Information Exhaust RequirementsOutside Ductwork Protection Maytag Co Multiple Common Dryer Venting Importantventingreminders Electrical Requirements Electrical InformationNON-REVERSING GAS Single-Phase Electrical Lead Connections For 110V Applications GAS Information Type of GAS Maytag Co 113394 Maytag Co Preparation for OPERATION/START-UP Preoperational Tests Basket Tumbler Coating Preoperational Instructions Dual Timer DryersShutdown Instructions Reversing Timer SPIN/DWELL AdjustmentsService SERVICE/PARTS InformationParts Cleaning Routine MaintenanceSuggested Cleaning Schedule Lubrication AdjustmentsLint Drawer Removal Data Label Information Sectionvii Procedure for Functional Check Replacement ComponentsMaytag Co Phase Manual Reset Burner HI-LIMIT InstructionsDual Timer Sensoractivated Fire Extinguishing S.A.F.E. System F.E. System In ActionInstallation Typical Water Supply F.E. System Theory of Operation F.E. System Water Valve Check F.E. System Diagnostics Messages Maytag Co 10/30/08