American Dryer Corp MDG75PNH, MDG75MNV installation manual Installation

Page 44

INSTALLATION

1.Requirements

The S.A.F.E. system must be supplied with a minimum water pipe size of 1/2” and be provided with 40 psi +/- 20 psi (2.75 bar +/- 1.37 bar) of pressure. For use of optional manual bypass, a second source with the same piping and pressure requirements is required.

Flexible 1/2 feeds must be provided to avoid damage to electric water solenoid valve by vibration.

IMPORTANT: Flexible supply line/coupling must be used. Solenoid valve failure due to hard plumbing connections WILLVOID WARRANTY.

If the rear area of the dryer, or the water supply is located in an area where it will be exposed to cold/ freezing temperatures, provisions must be made to protect these water lines from freezing.

WARNING: If the water in the supply line or water solenoid valve freezes, the S.A.F.E. system will be INOPERATIVE!!

IMPORTANT: Appliance is to be connected to the water mains using a new hose set and the old hose set should not be reused.

2.Water Connections:

The water connection is made to the 3/4”-11.5 NH hose adaptor of the electric water solenoid valve, located at the rear upper midsection of the dryer (refer to the photograph).

The water solenoid valve has a 3/8” M.P.T. connection supplied with a 3/4”-11.5 NH hose adapter to provide the minimum 1/2-inch supply (feed) line. Flexible supply line/coupling must be used in an effort to avoid damaging the electric water solenoid valve.

NOTE: The 3/4”-11.5 NH is a standard hose coupling screw thread. It is not to be confused with 3/4” N.P.T. The sealing of an NH connection is made with a washer opposed to the mating threads of an N.P.T. assembly. The two (2) thread designs are not compatible.

IMPORTANT: Flexible supply line/coupling must be used. Solenoid valve failure due to hard plumbing connections WILL VOID WARRANTY. It is recommended that a filter or strainer be installed in the water supply line.

40

Maytag Co.

113394 - 8

Image 44
Contents MDG75PNH and MDG75MNV Installation Manual Retain This Manual In a Safe Place For Future Reference For Your Safety Page Table of Contents Section Procedure for Functional Check Safety Precautions SectionMaytag Co 113394 Specifications SpecificationsSpecifications Gas Component Identification Maytag Co 113394 Installation Procedures Location RequirementsUNPACKING/SETTING UP Dryer Enclosure Requirements Fresh AIR Supply Requirements Exhaust Requirements General Exhaust Ductwork InformationOutside Ductwork Protection Maytag Co Multiple Common Dryer Venting Importantventingreminders Electrical Information Electrical RequirementsNON-REVERSING GAS Single-Phase Electrical Lead Connections For 110V Applications GAS Information Type of GAS Maytag Co 113394 Maytag Co Preparation for OPERATION/START-UP Preoperational Tests Basket Tumbler Coating Dual Timer Dryers Preoperational InstructionsReversing Timer SPIN/DWELL Adjustments Shutdown InstructionsParts SERVICE/PARTS InformationService Suggested Cleaning Schedule Routine MaintenanceCleaning Adjustments LubricationLint Drawer Removal Data Label Information Procedure for Functional Check Replacement Components Sectionvii Maytag Co Dual Timer Manual Reset Burner HI-LIMIT InstructionsPhase F.E. System In Action Sensoractivated Fire Extinguishing S.A.F.E. SystemInstallation Typical Water Supply F.E. System Theory of Operation F.E. System Water Valve Check F.E. System Diagnostics Messages Maytag Co 10/30/08