Pelican PUV-Basic owner manual Water Quality Requirements

Page 10

OVERVIEW

INSTALLATION

OPERATION

MAINTENANCE

WARRANTY

1Sample valve: Allows for sampling of raw water.

2Shut-off valve: Required to allow maintenance of pre-treatment equipment.

3Pre-treatment (illustrative only): For the UV system to operate effectively, the water should meet certain water quality parameters, as outlined below. To meet these, pre-treatment of the water may be required. Pre- treatment equipment must be installed BEFORE the UV chamber. Pre-treatment systems can be comprised of one or more of the following elements: sediment filters; carbon filters; iron removal systems; water softeners; cyst reduction filters, etc.

Water Quality Requirements:

Iron:

< .3 PPM (.3 mg/L)

Hardness:

< 120 PPM (7 Grains Per Gallon)

% UVT:

> 75%

Tannins:

< 0.1 PPM

IMPORTANT:

A 5 micron (nominal) sediment filter must be installed before the UV system and after any water softening equipment

4Bypass shut-off valve: Bypass line and valve are optional. Intended to provide emergency water supply in the event that the UV system is unavailable.

5Shut-off valve: Required to allow maintenance of UV system.

6Sample valve: Allows for sampling of water entering UV chamber; necessary in order to confirm water being treated is of adequate quality.

7UV chamber: Provides disinfection of the water. Must install Plus model chambers vertically.

8CoolTouchTM valve: Drains water from the chamber that’s been warmed by the lamp during periods of no flow.

9Flow Restrictor: Restricts water from flowing over the maximum NSF certified flow rate ensuring an adequate UV dose is maintained.

10Sample valve: Allows for sampling of water immediately following UV treatment; necessary in order to confirm proper operation of UV system.

11Solenoid valve: Optional piece of equipment supplied by VIQUA for PUV-8 and PUV-16 models. Must be used with a junction box. Allows water supply to be shut-off when proper purification cannot be

assured.

Note: If the ground from your electrical panel is tied to your copper water lines, and you are using a solenoid valve, installation of an approved ground strap is required. This ground strap will maintain continuity between the lines that have been cut to install the solenoid. Check your local electrical code for the correct clamp and cable size.

12Shut-off valve: Required to allow maintenance of UV system.

13Junction box: An optional piece of equipment for PUV-8 and PUV-16 models. Powers solenoid valves, remote alarms and auto-dialers.

14Power supply: Powers and controls the UV lamp and other devices. Provides human interface, displaying information and allowing control inputs (such as muting the audible alarm).

15Power source: Provides power to the power supply. For safety reasons the outlet must be protected by a

Ground Fault Circuit Interrupter (GFCI). NOTE: to protect the power supply, a UL1449 certified (or equivalent) transient voltage surge suppressor is required.

8

Image 10
Contents PUV-8 Potential Safety Measures Hazard Safety Instructions Table of Contents What Model do I HAVE? PUV-Basic PUV-8 PUV-16Specifications General All ModelsPart ComponentsPart Number Components All Models Part Model Part NumberDimensions and Layout Water Quality Requirements Installing the UV System Gfci Disinfecting the Water Lines Allow water to fill Installation Overview Operation Maintenance Warranty Overview Operationinstallation Green Yellow Flashing red Solid redTroubleshooting Symptom Possible cause Possible solutionOverview Installation Operation Maintenancewarranty Lamp tab Sleeve bolt Operationmaintenance Warranty Warranty Our Commitment