Desa CHDV41N/P, CHDV37N/P installation manual Vent Pipe Connections

Page 9

OWNER’S MANUAL

VENTING INSTALLATION

Continued

3.Attach vent pipe assembly to the fire- place. Set fireplace in front of it’s per- manent location to insure minimum clearances. Mark the wall for a 10" square hole (for noncombustible ma- terial such as masonry block or con- crete, a 7 1/2" diameter hole is accept- able). See Figure 12. The center of the hole should line up with the center-line of the horizontal rigid vent pipe. Cut a 10"x10" (254mm x 254mm) square hole through combustible exterior wall (7 1/2" [190mm] diameter hole if non- combustible). Frame as necessary (see Figure 12).

 

4" Clamp

Female

7" Clamp

Locking

 

Lugs

 

 

Spacer

 

Spring

Male

4" Flex

Pipe

Slots

 

 

7" Flex

 

Pipe

Rigid Vent Pipe Flexible Vent Pipe

Figure 11 - Vent Pipe Connections

Vent Opening

Combustible Wall

10"

(254mm)

10"

(254mm)

(Framing

4.Apply a bead of non-hardening mastic around the outside edge of the vent cap. Position the vent cap in the center of the 7 1/2" or 10" hole on the exterior wall with the arrow on the vent cap pointing up. Insure proper clearance of 1" to combustibles is maintained. At- tach the vent cap with four wood screws supplied (see Figure 13). Note: Re- place the wood screws with appropri- ate fasteners for stucco, brick, concrete, or other types of siding.

WARNING: Do not recess vent termination in to any wall. This will cause a fire hazard.

For vinyl siding use vinyl siding stand- offs between vent cap and exterior wall. The vinyl siding standoff prevents ex- cessive heat from melting the vinyl sid- ing material. Bolt the vent cap to the standoff. Apply non-hardening mastic around outside edge of the standoff in- stead of the vent cap assembly. Use wood screws provided to attach the standoff. See Figure 14.

5.Slide the wall thimble over the vent pipe before connecting the horizontal run to the vent cap (see Figure 15).

Apply Mastic to All Four Sides

UP

Wood

Screw

Vent Cap

Figure 13 - Installing Horizontal Vent Cap

6.Carefully move the fireplace with vent assembly attached toward the wall and insert the vent pipe into the horizontal termination. The pipe overlap should be a minimum of 1 1/4". Apply silicone to the outer pipe connection. Fasten all vent connections with screws provided. Refer to Fireplace Installation on page 16 for instructions on securing unit to framing or floor.

7.Slide the wall thimble against the inte- rior wall surface and attach with screws provided (see Figure 15).

Cut Vinyl Siding

Away to Fit

Standoff

Wood Screw

Standoff

UP

Nut

Bolt

Apply Mastic

to All Four Sides Vent Cap

Figure 14 - Installing Vinyl Siding Standoff

Interior Wall

Surface

Wall

Thimble

Vent Opening

Detail)

Screw

Vent Cap

Noncombustible Wall

7 1/2" (190mm)

Figure 12 - Vent Opening Requirements

(Horizontal

Horizontal

Vent Pipe

Termination)

 

Figure 15 - Connecting Vent Cap with Horizontal Vent Pipe

Continued

105542

9

Image 9
Contents For Your Safety For Your Safety What to do if YOU Smell GASCHDV37N/PA,B and CHDV41N/PA,B DIRECT-VENT Fireplace NATURAL/PROPANE/LP Safety InformationProduct Identification Product FeaturesLocal Codes Glossary TermsLocation and Space Requirements PRE-INSTALLATION PreparationClearances Framing and FinishingLocation of Vent Termination PRE-INSTALLATION Preparation General VentingGeneral Venting Installation Precautions Venting InstallationInstallation Planning Installing Vent System in a ChaseSnorkel Termination Installation for Horizontal TerminationVent Pipe Connections Horizontal Termination Configuration for Rigid Venting Horizontal Termination ConfigurationsVenting with Two 90 Elbows Installation for Vertical Termination Flat Ceiling InstallationCathedral Ceiling Installation Venting with One 90 Elbow Vertical Termination ConfigurationsVertical Venting Parts Lists for Venting Kits and Components High Altitude InstallationComfort Glow Rigid Venting Comfort Glow Flexible VentingInstalling Optional Blower Accessory Fireplace InstallationInstalling GA3750/CDA3620T Blowers Check GAS TypeIf your fireplace system is installed Installation Items Needed Installing GAS Piping to Fireplace LocationInstallation Items Needed Connecting Fireplace to GAS SupplyPressure Testing Gas Supply Piping System Checking GAS ConnectionsClose manual shutoff valve see Fig- ure Pressure Testing Fireplace Gas ConnectionsIncluded Installing Battery into Receiver Wireless HAND-HELD Remote ControlInstalling 9-Volt Battery in Hand- Held Remote Control Unit REMOVING/REPLACING Glass DoorAttaching Magnetic Decorative Brass Strips Installing Optional Brick Liner CD8037A/ CD8041Fireplace Models CHDV37N/P and CHDV41N/P Installing LOGS, Lava Rock and Glowing EmbersManual Lighting Procedure For Your Safety Read Before LightingOperating Fireplace Lighting InstructionsHAND-HELD Remote Operation Operating Optional Blower AccessoryPilot Assembly Inspecting BurnersBurner Flame Pattern Glass Door Cleaning and MaintenancePilot and Burners LogsObserved Problem Possible Cause TroubleshootingObserved Problem Possible Cause Remedy Gas leak. See Warning statement Wiring Diagram Replacement PartsService Hints Technical ServiceCHDV37NA,B CHDV37PA,B CHDV41NA,B CHDV41PA,B SpecificationsManual Blower KIT GA3750 AccessoriesTHERMOSTATICALLY- Controlled Blower KIT CDA3620T GMC41F41 Walnut Stained Hardwood VeneerCHDV37NA,B CHDV41NA,B Illustrated Parts BreakdownDIRECT-VENT Fireplace CHDV37NA,B CHDV41NA,B Parts ListCHDV37PA,B CHDV41PA,B DIRECT-VENT Fireplace CHDV37PA,B CHDV41PA,B Warranty Information