Desa DVF34P Installing GAS Piping to Fireplace Location, Installation Items Needed

Page 18

DVF34, DVF34P

DIRECT-VENT FIREPLACE (NATURAL/PROPANE/LP)

FIREPLACE INSTALLATION

Continued

INSTALLING GAS PIPING TO FIREPLACE LOCATION

WARNING: A qualified ser- vice person must connect fire- place to gas supply. Follow all local codes.

CAUTION: For propane/LP units, never connect heater di- rectly to the propane/LP supply. This heater requires an external regulator (not supplied). Install the external regulator between the heater and propane/LP supply.

Installation Items Needed

Before installing fireplace, make sure you have the items listed below.

external regulator (supplied by installer)

piping (check local codes)

sealant (resistant to propane/LP gas)

equipment shutoff valve *

test gauge connection *

sediment trap

tee joint

pipe wrench

approved flexible gas line with gas con- nector (if allowed by local codes) (not provided)

CAUTION: Use only new, black iron or steel pipe. Inter- nally-tinned copper tubing may be used in certain areas. Check your local codes. Use pipe of 1/2" diameter or greater to allow proper gas volume to fireplace. If pipe is too small, undue loss of pressure will occur.

Installation must include an equipment shutoff valve, union, and plugged 1/8" NPT tap. Locate NPT tap within reach for test gauge hook up. NPT tap must be upstream from fireplace (see Figure 34).

Propane/

LP Supply

Tank

External

Regulator

Vent

Pointing

Down

Figure 33 - External Regulator with Vent Pointing Down (Propane/LP Only)

CSA Design-Certified Equipment Shutoff Valve with 1/8" NPT Tap*

IMPORTANT: Install equipment shutoff valve in an accessible location. The equip- ment shutoff valve is for turning on or shutting off the gas to the appliance.

Check your building codes for any special requirements for locating equipment shutoff valve to fireplaces.

Apply pipe joint sealant lightly to male threads. This will prevent excess sealant from going into pipe. Excess sealant in pipe could result in clogged fireplace valves.

CAUTION: Use pipe joint seal- ant that is resistant to liquid pe- troleum (LP) gas.

We recommend that you install a sediment trap/drip leg in supply line as shown in Figure 34. Locate sediment trap/drip leg where it is within reach for cleaning. Install in piping system between fuel supply and heater. Locate sediment trap/drip leg where trapped matter is not likely to freeze. A sediment trap traps moisture and contami- nants. This keeps them from going into fireplace gas controls. If sediment trap/drip leg is not installed or is installed wrong, fireplace may not run properly.

*A CSA design-certified equipment shutoff valve with 1/8" NPT tap is an acceptable alternative to test gauge connection. Pur- chase the CSA design-certified equipment shutoff valve from your retailer.

For propane/LP connections only, the in- staller must supply an external regulator. The external regulator will reduce incoming gas pressure. You must reduce incoming gas pressure to between 11 and 14 inches of water. If you do not reduce incoming gas pressure, heater regulator damage could

Approved Flexible

Gas Line

3" Minimum

Natural - From Gas Meter (5" W.C. to 10.5" W.C. Pressure )

Propane/LP - From External Regulator (11" W.C. to 14" W.C. Pressure)

occur. Install external regulator with the vent pointing down as shown in Figure 33. Pointing the vent down protects it from freezing rain or sleet.

Cap Pipe Nipple Tee Joint

Sediment Trap/Drip Leg

Figure 34 - Gas Connection

*The CSA design-certified equipment shutoff valve may be supplied with the appliance or you can purchase it from your retailer.

18

106424

Image 18
Contents For Your Safety For Your Safety What to do if YOU Smell GASNatural GAS Model DVF34 PROPANE/LP GAS Model DVF34P Safety Information DVF34, DVF34P DIRECT-VENT Fireplace NATURAL/PROPANE/LPGlossary Terms Product IdentificationLocal Codes OperationLocation and Space Requirements PRE-INSTALLATION PreparationClearances Framing and FinishingPRE-INSTALLATION General Venting Preparation Location of VentTermination General Venting Installation Planning Venting InstallationInstallation Precautions Installing Vent System in a ChaseInstallation for Horizontal Termination Snorkel Termination with Drainage PipeRigid Vent Pipe Connections Horizontal Termination Configurations Horizontal VentingVenting with Two 90 Elbows Installation for Vertical Termination Flat Ceiling InstallationCathedral Ceiling Installation Vertical Termination Configurations Venting with Two 90 Elbow sVertical Venting High Altitude Installation Parts Lists for Venting Kits and ComponentsFMI Rigid Venting Installing GA3700/DA3610TA Blowers Fireplace InstallationInstalling Optional Blower Accessory Check GAS TypeIf your fireplace system is installed Installing GAS Piping to Fireplace Location Installation Items NeededConnecting Fireplace to GAS Supply Pressure Testing Gas Supply Piping SystemChecking GAS Connections Pressure Testing Fireplace Gas Connections Close equipment shutoff valve see Fig- ureInstalling Optional Wall Mount Switch GWMS2 Installing 9-Volt Alkaline Battery into ReceiverREMOVING/REPLACING Glass Door Installing Optional Brick Liner D8037A Attaching Magnetic Decorative Brass StripsInstalling LOGS, Lava Rock and Glowing Embers Installing Log NoOperating Fireplace For Your Safety Read Before LightingManual Lighting Procedure Lighting InstructionsPilot Assembly Operating Optional Blower AccessoryOperating Optional GWMS2 Wall Mounted Switch Inspecting BurnersCleaning and Maintenance Troubleshooting Observed Problem Possible CauseObserved Problem Possible Cause Remedy Gas leak. See Warning statement Service Hints Replacement PartsWiring Diagram Technical ServiceSpecifications DVF34 DVF34PIllustrated Parts Breakdown DVF34 DVF34PParts List DIRECT-VENT Fireplace DVF34 DVF34PAccessories 106424 Warranty Information