Weber 55159, Genesis Silver B Gas Grill manual Measure and drill holes

Page 16

Step 5

Measure and drill holes

You will need: Completed frame assembly, base panel, tape measure, and pencil.

CAUTION: Combustible materials should never be within 24 inches of the top, bottom, back or sides of the barbecue. Do not locate under overhead combustible construction.

Note - With the lid open the depth of the barbecue is 28 inches, front to back.

Set the completed frame assembly in position on your deck, concrete pad, or patio for anchoring. Measure the distance from the outside of the base plate to the outside of the other base plate. It should be 26 5/8” across. Figure 3.

Note: If the measurement is not 26 5/8” across adjust the legs as necessary so that the measurement is 26 5/8”.

Step 6

Typical installation of the base for an existing concrete patio, new pad or wood deck

CAUTION: Combustible materials should never be within 24 inches of the top, bottom, back or sides of the barbecue. Do not locate under overhead combustible construction.

Note - With the lid open the depth of the barbecue is 28 inches, front to back.

For anchoring, we recommend use of one of the following methods:

WARNING: Whichever method used, the base must be bolted down (anchored) at a minimum of four anchoring points (two per side) prior to barbecue assembly. One anchor in each corner of the base plate. Figure 5.

25

5/8

Figure 3

Place the base panel in between the legs to insure fit. Figure 4. Once the fit is established, remove the base panel and mark the holes.

CAUTION: A minimum of 2 bolts are required on each side.

You are now ready to anchor the base.

Figure 4

1

4

2

3

Figure 5

16

Image 16
Contents Owners Guide Page Warranty Customer Service Center Roselle Road, Suite Schaumburg, ILContents Operating area For Installation in Canada Gas supply testingGeneral Instructions StorageGenesis Silver-B Permamount NG Page Page Page Page General Specifications for Piping Typical natural gas supply installation to a wood deck Recommended concrete pad requirements Step Continue frame assemblyAssemble the frame Add Wrap-around Frame Panel Measure and drill holes Method 2 Concrete Method 1 ConcreteMethod 3 Concrete Method 4 Wood deck Add cooking box Connect barbecue gas supply line to the natural gas supply Install manifold bracketCheck all valves are off Install igniter Purge air from gas linesBARBECUE. Contact Weber-Stephen Customer Service Check for gas leaksInstall side panels Add base panelInstall Flavorizer Bars and Cooking Grates Install the bottom trayInstall Lid Add tool holders, control panel and burner control knobsInstall the condiment basket Install the accessory rack Complete accessory installationLighting To ExtinguishManual Lighting Periodic Cleaning CookingAfter a Period of Nonuse Drippings and greaseAnnual Maintenance Inspection and cleaning of the Spider/Insect screensGeneral Maintenance Main Burner Cleaning ProcedureWeber Spider/Insect Screen Replacing Main BurnersPage Crossover Ignition System Operations When burner is on HIGH. Flames do not run Burner does not light, or flame is low in High positionExperiencing flare-ups Burner flame pattern is erratic. Flame is low