1.4. AC Service Requirements
Follow local code requirements if they are different than the instructions in this manual. After checking the transformer connections as described in Paragraph 1.3, refer to Table
TABLE
Line Amperes | Disconnect Switch | Fuse Size Amps | |
000.0 | - 02.5 | 30A | 05 |
003.0 | - 04.5 | 30A | 07 |
005.0 | - 07.5 | 30A | 10 |
008.0 | - 11.0 | 30A | 15 |
011.5 | - 15.5 | 30A | 20 |
016.0 | - 18.0 | 30A | 25 |
018.5 | - 22.0 | 30A | 30 |
022.5 | - 27.0 | 60A | 35 |
027.5 | - 32.0 | 60A | 40 |
032.5 | - 40.0 | 60A | 50 |
040.5 | - 48.0 | 60A | 60 |
048.5 | - 64.0 | 80A | 80 |
065.0 | - 80.0 | 100A | 100 |
081.0 | - 95.0 | 125A | 125 |
096.0 | - 125.0 | 150A | 150 |
For voltages up to 240, use a 240 volt disconnect switch.
For voltages greater than 240 to 600, use a 600 volt disconnect switch.
•Two conductors and ground wire required for single phase.
•Three conductors and ground wire required for
1.5.Connecting AC Service to the Charger
1.5.1
Connect the AC service to the L1 and L2 terminals located at the end of the AC fuse block.
Note: If the charger has been ordered with an AC input
1.5.2 Three-Phase Models
Connect the AC service to the L1, L2 and L3 terminals located at the end of the AC fuse block.
Note: If the charger has been ordered with an AC input
6