HP SN6000B, SN3000B manual Attaching the outer rails

Page 4

4.Attach each outer rail as shown in Figure 5 (page 4).

The rails are labeled Left and Right to designate the left side and right side of the rack as viewed from the front of the cabinet.

Figure 5 Attaching the outer rails

a.Slide the rail over the rear mounting bracket.

b.Attach the front of the rail to a front rack upright column using two Phillips screws and adapter washers.

c.Attach the outer rail to the rear mounting brackets using a Phillips screw.

TIP: Tighten the rear screws just enough for the end of the screw to go through the rear bracket. Later in the procedure, you will need room to slide the inner rail between the screw head and the outer bracket.

5.From the front of the rack, slide the switch (with inner rails attached) onto the outer rails, taking care to align the inner rails with the attachment screws on the outer rails at the rear of the rack. See Figure 6 (page 4).

Figure 6 Installing the switch in the rack

6.When the switch is in place, secure the inner rails to the outer rails by tightening the screws at the rear of the rack.

7.At the front of the rack, run the switch power cords from the sides of the rack through the cutouts in the rail, and then connect them to the switch

power supplies. Connect two power cords to the 48-port switch. Connect one power cord to the 24-port switch. See Figure 7 (page 4).

IMPORTANT: Make sure that the power cords do not come in contact with any sharp edges.

NOTE: If you are configuring the second (optional) power supply, the 24-port switch will also have two power cords.

Figure 7 Connecting power and installing the plenum

1. Cutouts for power cords

3. Power switches

2. Power cable plugs

4. Plenum thumb screws

8.Connect the other end of the power cords to power sources on separate circuits to protect against AC failure. (Make sure that two power cords are connected to the 48-port switch and one power cord is connected to the 24–poort switch.)

NOTE: If you are configuring the second (optional) power supply, the 24-port switch will also have two power cords.

9.Power on the power supplies by setting the power switches to the ON position ().

The power supply LEDs are amber until the Power On Self Test (POST) is complete, and then change to green. The HP SN6000B 16Gb FC Switch takes several minutes to boot and complete POST.

NOTE: When installed, the plenum covers the power supply switches and LEDs. However, the LEDs are visible through the air holes in the front of the plenum.

10.Slide the plenum over the nonport side of the inner rails, taking care to bypass the power cables. See Figure 7 (page 4).

11.Tighten the thumbscrews to secure the plenum to the front of the rack.

Page 4

Image 4
Contents Verify the SN6000B 16Gb 48-port FC switch carton contents OverviewVerify the SN3000B 16Gb 24-port FC switch carton contents Attaching the inner rails to the switch Attaching the outer rails Install a standalone switch Power on the switchSwitch setup Connect the serial cableSet a static IP address Log in to the serial console portSet the date and time Switchadmin tsclockserver ntp1ntp2 Inserting a 16 Gb/s SFP+ transceiver in a Fibre Channel portVerify switch operation Set switch features