Soleus Air KFHHP-09-OD, KFHHP-12-ID, KFHHP-12-OD, KFIHP-09-ID Air Purging and Leakage Test

Page 18

Install the Outdoor Unit

Air Purging and Leakage Test

1.Remove the flare nuts of charging end from gas valve.

2.Connect the charging hose in the middle to the vacuum pump, then Low-pressure (Lo) end should be connected to charging end of gas valve. (Shown in Fig. 9)

3.Open the vacuum pump to evacuate. When multi-meter indicates 1 bar, fully tighten Lo handle of manifold valve and stop evacuation. Keep it for over 15 minutes to ensure the pressure is constant.

4.Remove bonnets of gas and liquid valve.

5.Slightly loosen core of liquid valve with hexagon wrench until the pressure exceeds 0 bars.

6.Remove charging hose from charging end of gas valve and screw the flare nuts of charging end.

7.Open cores of gas and liquid valve entirely by hexagon wrench.

8.Tighten the bonnets of gas and liquid valve, and then test whether there is any leakage or not.

- 16 -

Image 18
Contents Wall Mounted Mini Split Heat Pump Air Conditioner Indoor Unit Outdoor UnitTable of Contents Structure and Operation Name of Each PartInstructions before Use Adjust the guide louver and change Specification and Technical Data KFIHP-09-ID KFHHP-12-ID KFIHP-09-OD KFHHP-12-ODRemote Control Operation Function-Remote controlRemote Control Operation How to Insert Batteries General procedure OperationInstallation Location Indoor UnitOutdoor Unit Electric Wiring Grounding RequirementInstallation Dimension Diagram Important NotesInstallation Installation Install the Indoor Unit Install the Outdoor Unit Install the connection pipeElectric wiring connection Air Purging and Leakage Test Test Operation and Check after Installation Test OperationCare and Maintenance Care and MaintenanceTrouble Shooting Trouble ShootingProblem Check before UseTrouble Shooting Trouble Shooting Electrical Schematic Diagram Indoor Unit Electrical Schematic Diagram Outdoor Unit Warranty