ROBERTS GOR DON® BH-SERI E S SUBM IT TAL SHE E T

Reflector, U-Clip and Reflector Support Installation

The pictorial drawings of the heater construction in this section are schematic only and provide a general guideline of where hangers, reflector supports and U-clips are to be installed.

To ensure proper expansion and contraction move- ment of the reflectors, a combination of U-clips and reflector supports are used. The positioning of reflec-

tor supports and U-clips depend on the individual installation. Use either pop rivets or sheet metal screws instead of u-clips when installing end caps and joint pieces in areas where impact and high wind may be a factor. The following rules must be observed.

1.The first reflector after the burner must be affixed in the middle of the reflector with a reflector support and tight screws.

End

First Reflector

U-Clips

Overlap must be a

6"

minimum of 6" (16 cm)

(16 cm)

2.The overlap at the first and second reflector is a slip overlap. Thereafter, every third reflector joint is a slip overlap. A slip overlap is achieved by either:

a.) both reflectors lay inside a hanger. (no reflector support needed).

b.) using a reflector support with loose screws at the reflector overlap.

 

Tight

 

Sheet Metal

Wire Form

Screw

 

Reflector Support

Strap

Option B

Slip Overlap Reflector

Reflector

Support

Loose screws

loosened 1/16"

(2 mm) to allow

slippage.

Option A

Slip Overlap

3.The remaining reflector overlaps require a non-slip overlap connection. To affix the reflectors together in a non-slip overlap either:

a.) use reflector support and tight screws.

b.) if both reflectors lay inside a hanger, u-clips or sheet metal screws may be used.

This section of three reflectors joined together must be affixed to the tube with at least one reflector support with tight screws.

Option A

Non-Slip Overlap

Option B

Non-Slip Overlap

Reflector

Tight

screws

U-Clip

(2 clips per

non-slip overlap inside a hanger)

© 2004 Roberts-GordonBEFORE IN STALLATI ON AND OPER ATI ON OF HEATI NG EQUIPMENT, READ AND U NDERSTAND THE INSTALLATION, OPERATIO N AND SERVICE MANUAL .

APPLICATION S, ENGI NEERING AND DETAI LED GUID ANCE ON SYSTEMS DESIGN, INSTALLATI ON AND PRODUCT PERFORMANCE IS AVAI LABLE UPON REQUEST. ROBERTS GORDON® PRODUCTS ARE TO BE INSTALLED ONLY IN ACCORDANCE WI TH LOCAL LAWS, CODES AND REGULATIONS, AND ONLY BY A CONTRACTOR QUALI FIED I N THE I NSTALLATION AND SERVICE OF GAS-FIRED HEATING EQUI PMENT.

Image 17
Contents Copyright 2004 Roberts-Gordon N170601NA Rev D 07/04 Roberts-Gordon2004 Contents of Core and Extension Packages Standard Parts ListContents of BH-Series Burner Carton General Specifications Standard Reflector Inches Centimeters Model Clearances to CombustiblesOne Side Reflector Inches Centimeters Two Side Reflectors Inches CentimetersInches Centimeters Tilt Reflector Inches CentimetersTube, Full Inches Centimeters Model ModelLower Clearance Shield Inches Centimeters Tube, Opposite 45 Reflector Inches Centimeters ModelBH-80 153 166 BH-40 BH-60 138 150BH-40 Venting InchesVent BH-60 Infrared Tubes Pipes BH-80 BH-100 BH-115/125 BH-140/150 BH-175/200BH-SERIES Assembly Overview BH-Series Linear Assembly Overview Critical Hanger Placement Heater InstallationBH-Series Linear Layout Overview Weld Must be to the bottom of the tube Burner Tube InstallationBurner Tube Hook 91907302 Tube/Reflector Hanger 03090100Coupling and Tube Assembly Tube Clamp Package InstallationOpen ClosedTighten slide bar as shown below Correct Slide DimensionsPosition 229 cm ± 305 25 cm Total Overall Tube LengthHanger Burner Tube Reflector Turbulator InstallationReflector Installation Overlap must be a Minimum of 6 16 cm Reflector, U-Clip and Reflector Support InstallationScrew Reflector SupportExtra chain min 12 30 cm Burner Gasket Lock Burner InstallationHook Burner Tube Bolt Torque 120 Bolt 94273914 BurnerBH-Series U-Tube Assembly Overview Optional Heater AccessoriesTube, Standard Tube, FullBH-Series U-Tube Layout Overviews BH-175 BH-200 BH-140 BH-150 BH-175 BH-200Tube Coupling Elbow Package Configuration Elbow InstallationReflector Joint Installation Attach Reflector Joint Reflector Joint DetailJoint Reflector Side Extension Bracket InstallationSide Reflector Installation Shield Support Strap Assembly Lower Clearance Shield InstallationTWO-FOOT Decorative Grille Installation Grille InstallationShield Frame Shield InstallationReflector Side Extension Installation One-Foot Decorative Grille Bracket ONE-FOOT Decorative Grille InstallationDecorative Grille Joint Piece and ReinforcementElbow End Piece and Reflector End CapReflector joint piece End PieceSilicone Cap Installation Protective Grille InstallationHorizontal Ventilation 4 10 cm Pipe VentingVertical Ventilation 4 10 cm Pipe Combustible or Non-Combustible Wall OnlyTjernlund VH1-6 or Equivalent Common Sidewall VentingOutside Wall Vent Terminal 6 15 cm 90502101Top View Roberts-Gordon Common Vertical VentingVent Cap 4 10 cm 90502300 Vertical Outside Air Supply for Single Heater InstallationOutside Combustion AIR Supply Vent Cap Vertical Outside Air Supply for Double Heater InstallationVent Cap Wall Outside Vent Cap 6 15 cm 90502302Shown without blower assembly Gas Connection with Stainless Steel Flex ConnectorGAS Piping Shut-Off ValveLine Voltage Thermostat Wiring WiringBurners Maximum 5 BurnersSpdt Transformer Relay Low Voltage Thermostat WiringLow Voltage Thermostat BlackBH-Series Ladder Diagram BH-Series Internal WiringBlower Transformer Pressure Switch Gap Electrode Ground Power Sense Spark Valve Ignition Module Gas ValveElectrical Connection to the Burner Pressure Switch Internal Burner DiagramROBERTS-GORDON will not PAY for Warranty is Void ifLimitations on Authority Representatives Canada