Lennox International Inc EL280DF Electrical, Interior MAKE−UP BOX Installation

Page 18

Leak Check

After gas piping is completed, carefully check all piping connections (factory− and field−installed) for gas leaks. Use a leak detecting solution or other preferred means.

NOTE − If emergency shutoff is necessary, shut off the main manual gas valve and disconnect the main power to the furnace. The installer should properly label these devices.

CAUTION

Some soaps used for leak detection are corrosive to certain metals. Carefully rinse piping thoroughly af- ter leak test has been completed. Do not use matches, candles, flame or other sources of ignition to check for gas leaks.

The furnace must be isolated from the gas supply system by closing its individual manual shut-off valve during any pressure testing of the gas supply system at pressures greater than or equal to 1/2 psig (3.48 kPa, 14 inches w.c.).

IMPORTANT

When testing pressure of gas lines, gas valve must be disconnected and isolated. See figure 18. Gas valves can be damaged if subjected to pressures greater than 1/2 psig (3.48 kPa, 14 inches w.c.).

INTERIOR MAKE−UP BOX INSTALLATION

(Right Side)

MAKE−UP

BOX

Cut the two wire ties to extend power wires for right side only

FIGURE 19

Refer to figure 20 for schematic wiring diagram and trou- bleshooting and table 9 for field wiring.

The power supply wiring must meet Class I restrictions. Protected by either a fuse or circuit breaker, select circuit protection and wire size according to unit nameplate.

NOTE − Unit nameplate states maximum current draw. Maximum over−current protection allowed is 15 AMP.

MANUAL MAIN

SHUT−OFF VALVE WILL NOT HOLD NORMAL TEST PRESSURE

1/8 NPT PLUG

CAP

ISOLATE

GAS VALVE

FURNACE

Holes are on both sides of the furnace cabinet to facilitate wiring.

Install a separate (properly sized) disconnect switch near the furnace so that power can be turned off for servicing.

Before connecting the thermostat, check to make sure the wires will be long enough for servicing at a later date. Make

FIGURE 18

Electrical

ELECTROSTATIC DISCHARGE (ESD)

Precautions and Procedures

CAUTION

Electrostatic discharge can affect elec- tronic components. Take precautions to neutralize electrostatic charge by touching your hand and tools to metal prior to handling the control.

The unit is equipped with a field make−up box on the left hand side of the cabinet. The make−up box may be moved to the right side of the furnace to facilitate installation. If the make−up box is moved to the right hand side, clip the wire ties that bundle the wires together. Secure the excess wire to the existing harness to protect it from damage.

sure that thermostat wire is long enough to facilitate future removal of blower for service.

Complete the wiring connections to the equipment. Use 18−gauge wire or larger that is suitable for Class II rating for thermostat connections.

Electrically ground the unit according to local codes or, in the absence of local codes, according to the current Na- tional Electric Code (ANSI/NFPA No. 70). A green ground wire is provided in the field make−up box.

NOTE − The EL280DF furnace contains electronic compo- nents that are polarity sensitive. Make sure that the furnace is wired correctly and is properly grounded.

Accessory Terminals

One line voltage ade terminal is provided on

the furnace integrated control. See figure 21 for integrated control configuration. This terminal is energized when the indoor blower is operating. Any accessory rated up to one amp can be connected to this terminal with the neutral leg

Page 18

Image 18
Contents Installation Instructions EL280DF Table of ContentsUnit Dimensions − inches mm TOP ViewSafety Information EL280DF Gas FurnaceShipping and Packing List Use of Furnace as Construction Heater GeneralCombustion, Dilution & Ventilation Air Equipment in Confined Space ALL AIR from Inside Equipment in Confined Space Downflow Installation NON−COMBUSTIBLE Floor Opening SizeCombustible Floor Opening Size Setting Equipment Filters Duct System VentingTables for installations Mm of connector diameter as follows MIN MAX FAN + FAN FAN + NAT Gas Piping Carbon Monoxide Poisoning HazardGas Pipe Capacity − ft3/hr m3/hr Interior MAKE−UP BOX Installation ElectricalElectrostatic Discharge ESD Page Field Wiring Applications OFF EL280DF Schematic Wiring Diagram Integrated Control TWO−STAGE Integrated ControlFor Your Safety Read Before Lighting Unit Start−UpEL280DF Gas Pressure AdjustmentGAS Meter Clocking Chart DialProper Combustion High AltitudeOther Unit Adjustments Heat FAN-OFF Time in SecondsHeating Sequence of Operation Service Electrical SHOCK, Fire Or Explosion HazardRepair Parts List EL280DF BURNER, Combustion AIR Inducer AssemblyHeat Exchanger Removal Start−Up & Performance Check List Unit Operation Cooling ModeTemperature Rise Drain Line
Related manuals
Manual 7 pages 17.85 Kb

EL280DF specifications

Lennox International Inc. has been a leader in the HVAC (Heating, Ventilation, and Air Conditioning) industry for decades, consistently delivering high-quality and energy-efficient products. Among their lineup, the Lennox EL280DF Gas Furnace stands out as an excellent option for homeowners seeking reliable heating solutions.

The EL280DF is a two-stage gas furnace that offers improved efficiency and comfort, making it an ideal choice for moderate climates. One of the main features of the EL280DF is its energy efficiency, boasting an AFUE (Annual Fuel Utilization Efficiency) rating of up to 80%. This means that a significant portion of the fuel consumed is converted into heating energy, resulting in lower energy bills and reduced environmental impact.

Another noteworthy characteristic of the EL280DF is its quiet operation. Equipped with advanced sound-dampening technologies, the furnace operates with minimal noise, ensuring that your home remains a serene environment. This is especially important during the colder months when the furnace is often in frequent use.

The EL280DF also employs a two-stage heating system, which allows it to operate at a lower capacity during milder temperatures and ramp up to full capacity during the coldest days. This feature not only enhances comfort by maintaining a more consistent temperature but also contributes to energy savings by reducing unnecessary energy consumption.

In terms of installation, the EL280DF is designed for flexibility. It can be configured for various types of homes and installations, making it suitable for both new constructions and system replacements. Its compact size allows it to fit in tight spaces, providing versatility in home design.

Moreover, the EL280DF is equipped with a durable heat exchanger that ensures longevity and reliability. Lennox has also included features like a self-diagnostic control board, making troubleshooting easier and enhancing the overall reliability of the system.

In conclusion, the Lennox EL280DF Gas Furnace is a remarkable combination of efficiency, quiet operation, and versatility. With its two-stage heating capabilities and advanced technologies, it stands as a solid choice for homeowners looking to invest in a durable and energy-efficient heating solution. Whether building a new home or upgrading an old system, the EL280DF promises comfort and reliability during the coldest months of the year.