Certificate of COMMISSIONING for the Premier SX Fire Alarm System installed at:

Address:

I/we being the competent person(s) responsible (as indicated by my/our signatures below) for the commissioning of the fire alarm system, particulars of which are set out below, CERTIFY that the said work for which I/we have been responsible complies to the best of my/our knowledge and belief with the recommendations of Clause 39 of BS5839-1:2002, except for the variations, if any, stated in this certificate

Name (in block letters):

Position:

Signature:

Date:

For and on behalf of:

 

Address:

 

Postcode:

The extent of liability of the signatory is limited to the system described below.

Extent of the installation work covered by this certificate.

Variations from the recommendations of clause 39 of BS 5839-1:2002 (see clause 7)

All equipment operates correctly

Installation work is, as far as can be reasonably ascertained, of an acceptable standard

The entire system has been inspected and tested in accordance with the recommendations of 39.2.c of BS 5839-1: 2002.

The system performs as required by the specifications prepared by:

Taking into account the guidance contained in section 3 of BS 5839-1: 2002, I/we have not identified any obvious potential for an unacceptable rate of false alarms.

The documentation described in Clause 40 of BS 5839-1:2002 has been provided to the user

The following work should be completed before/after (delete as applicable) the system becomes operational

The following potential causes of false alarms should be considered at the time of the next service visit:

Before the system becomes operational, it should be soak tested in accordance with the recommendations

of Clause 35.2.6 of BS 5839-1:2002 for a period of:(enter a period of 1 week, the period required by the design specification, or the period recommended by the signatory to this certificate, whichever period is the greatest, or delete if not applicable)

Approved Document No: GLT.MAN-102

PAGE 21

Issue: 1.3 Authorised: GH

Date: 9/6/2004

 

Image 21
Contents Page Purpose of a Fire Alarm SYSTEM……………………………………………… Purpose of a Fire Alarm System Fire Alarm Control Panel Safety IssuesDaily Inspection Responsible person mustAccessed Control Available to Authorised Users only Panel Indications & ControlsGeneral Controls LED Condition Panel Status HOW the Premier SX Indicates AN Alarm Fire / Zones Building evacuation procedure should now be followedFire Condition Different Types of Fault Fault ConditionSounder Fault Earth FaultReasons for Disabling Certain Parts of a Fire Alarm System DisablementsTo Disable a Zone AND/OR External Sounders To Enable a Zone AND/OR External SoundersWhat is a Sounder Delay Using Sounder DelaysFire Zone Information Fire Alarm System SummaryFire Alarm LOG Book Maintenance Work False Alarms ALL Events Other than Maintenance Work or False Alarms Commissioning the SYSTEM, Including P.S.E DESIGN, Installation & Commissioning CertificatesName in block letters Installation & Commissioning Recommendations Address Address Address