g
7. START-UP
GE Capacitor & Power Quality Products
Safety Precautions
Before startup, observe the following warnings and instructions:
WARNING
Internal components of the filter are at line potential when the filter is connected to the utility. This voltage is extremely dangerous and may cause death or severe injury if you come in contact with it.
WARNING
After disconnecting the utility power, wait at least 5 minutes before doing any work on the filter connections. After removing power, allow at least five minutes to elapse and verify that the capacitors have discharged to a safe level before contacting internal components. Connect a DC voltmeter across the capacitor terminals 1, 2 and 3 on terminal block 1TB. Start with the meter on the highest scale and progressively switch to a lower scale as the indicated voltage falls below the maximum value of the scale used.
Sequence of Operation
1.Read and follow safety precautions.
2.After installation, ensure that:
•All filter ground terminals are connected to ground.
•Power wiring to the utility, drive and motor is in accordance with the installation and connection instructions in Chapter 5.
46 | May 2003 |