regardless of air density. Good quality combustion and high efficiency are assured without special adjustment or changes to the heater.

2J. Electric Wiring

2J-1. Electrical Power

The Hi-E2requires electrical power from a 115V, 60 Hz source. Wiring connections must be made exactly as shown in the wiring diagram (See Figure

14). Grounding must be provided as required by the prevailing electrical code.

Connect wiring inside the junction box , which is on the right side of the heater and is accessible through the door opening. Line voltage connections must be made within this box. A labeled green grounding screw is provided in the junction box for a grounding wire (see Figure 15).

Wiring should include a means to prevent operation of the heater when there is no water flow. This is typically done with a time clock “Fireman’s Switch” as discussed in Section 2J-3.

ATTACH

GROUNDING

WIRE TO GREEN

GROUNDING

SCREW

Figure 15. Field Wiring Connections.

Figure 16. Typical Time Clock Wiring.

Figure 17. Terminal Block for Fireman’s Switch or Remote Control Wiring.

2J-2. Bonding

The National Electrical Code and most other codes require that all metallic components of a pool structure, including reinforcing steel, metal fittings and above ground equipment be bonded together with a solid copper conductor not smaller than a number 8 wire. The heater, along with pumps and other such equipment must be connected to this bonding grid. A special labeled bonding lug is provided on the right side of the heater to accommodate this requirement.

2J-3. Auxiliary Time Clock Wiring

If a time clock is provided to control the pool filter pump, it should have a separate low-voltage (Fireman’s) switch for the heater. Route the heater’s

24 VAC control circuit through this switch as shown in Figures 16 and 17. To do this, remove the “jumper” from the terminal block in the heater control compartment. Connect two wires to this terminal block and route them to the Fireman’s switch at the time clock. Provide wiring of at least 18 gauge with insulation at least 3/64" thick and having a temperature rating of at least 90oC.

2J-4. Remote Operation

The Hi-E2pool/spa heater controls can be wired for remote operation. Teledyne Laars and Jandy remote controls are available through the local dealer or distributor. The CS-02 remote control switches between the two temperature controllers and turns the heater on and off. The CS-04 has the same controls as the CS-02 and includes a remote temperature controller.

An interrupt (On-Off) type remote control can be connected by removing the jumper wire on the terminal block located in the control compartment (see Figure

17)and connecting the two wires from the remote to the two terminals on the terminal block. This type of remote control will turn the heater on or off, but will not switch between the two temperature controllers on the Flex-Temp control panel.

Image 12
Contents Installation Hi-E2 Model EHE Gas-Fired Pool Spa Heater Table of Contents Installation Instructions General Information2B. Heater Assembly and Preparation 2D. Installation Clearances2E. Outdoor Installation Installation at High Elevation2F. Outdoor Shelter Installation Canada 2G. Indoor Installation2G-1. Preparation of Heater For Indoor Installation United States2G-2. Combustion Air Requirements for One-Pipe Installation 2G-3. Two-Pipe Installation Direct Vent2G-3a. Connection of Combustion Air Pipe 2G-3b. Piping MaterialsInstallation 2G-3d. Combustion Air and Vent Pipe2G-3c. Size and Length of Combustion Air and Vent Piping Indoor Vent Connection, Hi-E2 Pool Heater 2G-3e. Room Ventilation 2H. Condensate Disposal2I. Gas Supply and Piping High Elevation 60Hz2J. Electric Wiring 2J-1. Electrical Power2J-3. Auxiliary Time Clock Wiring 2J-2. Bonding2K. Water Piping 2K-1. Reversal of Heater Water Connections2K-3. Connections at Heater 2K-4. Pressure Relief Valve 2K-5. Automatic Chlorinators Chemical Feeders2L. Start-up and Adjustment 2L-1. Normal Operation2L-5. Adjustment of Water Pressure Switch 2L-2. Start-up2L-3. Condensate 2L-4. Gas Pressure2L-6. Water Temperature Rise Operating Instructions3A. Start-Up Procedure 3B. Temperature Controls3C. Lighting and Shutdown 3D. Water Chemistry3E. Spa/Hot Tub Safety Rules 3D-2d. Testing3F. Swimming Pool Energy Savings Tips 3D-2c. Corrosion3G. Seasonal Care 3H. Periodic Inspection3G-1. Spring and Fall Operation 3G-2. WinterizingMaintenance and Service 4A. General3H-2. Professional Inspection 4B. Induced-Draft Combustion System 4C. Heater Components and Their Operation4E. Electrical Trouble Shooting 4E-1 V Electrical Power Supply4D. Combustion Air Filter 4E-2. Control Circuit Trouble Shooting 4E-2a. Transformer4E-2b. Fuse 4E-2c. Fireman Switch and External Interlocks 4E-2d. Limit Switches4E-2e. Water Pressure Switch 4E-2f. Temperature Control4F. Venturi Combustion Flow System 4F-2. Venturi System Checkout 4F-2a. Unfired Venturi Differential Pressure4F-2b. Gas Pressure Offset 4F-2c. Gas Orifice Differential4F-3. Air Flow Investigation 4F-3a. Combustion Air Flow4G. Combustion Condensate 4F-3b. Flow in Heater and Vent4F-4. Fuel Gas Type and Gas Orifice Size 4F-5. High Elevation OperationCapacities and Dimensions 4H. Major Component Service5A. General Information Replacement Parts 6A. Parts ListExploded View of the Hi-E2 Limited Warranty