GAS SUPPLY

The gas line can be routed either through the floor or wall. The gas line opening should be made at this time. Location of the opening will be determined by the position of floor joists and the valve and union used for servicing.

Gas Supply

Check all local codes for requirements, especially for the size and type of gas supply line required.

Recommended Gas Pipe Diameter

Pipe Length

Schedule 40 Pipe

Tubing, Type L

 

Inside Diameter

Outside Diameter

 

Nat.

L.P.

Nat.

L.P.

0-10 feet

1/2”

3/8”

1/2”

3/8”

0-3 meters

12.7mm

9.5mm

12.7mm

9.5mm

10-40 feet

1/2”

1/2”

5/8”

1/2”

4-12 meters

12.7mm

12.7mm

15.9mm

12.7mm

40-100 feet

1/2”

1/2”

3/4”

1/2”

13-30 meters

12.7mm

12.7mm

19mm

12.7mm

100-150 feet

3/4”

1/2”

7/8”

3/4”

31-46 meters

19mm

12.7mm

22.2mm

19mm

Note: Never use plastic pipe. Check to confirm whether your local codes allow copper tubing or galvanized.

Note: Since some municipalities have additional local codes, it is always best to consult your local authority and installation code.

3 9/16”

GAS INLET IN BOTTOM

(90mm)

OF HEATER

1 11/16” (43mm)

TO WALL

VIEW FROM TOP OF HEATER

Figure 1

Installing a New Main Gas Cock

Each appliance should have its own manual gas cock.

A manual main gas cock should be located in the vicinity of the unit. Where none exists, or where its size or location is not ad- equate, contact your local authorized installer for installation or relocation.

Compounds used on threaded joints of gas piping shall be resistant to the action of liquefied petroleum gases. The gas lines must be checked for leaks by the installer. This should be done with a soap solution watching for bubbles on all exposed connections, and if unexposed, a pressure test should be made.

Never use an exposed flame to check for leaks. Appliance must be disconnected from piping at inlet of control valve and pipe capped or plugged for pressure test. Never pressure test with appliance connected; control valve will sustain damage!

A gas valve and ground joint union should be installed in the gas line upstream of the gas control to aid in servicing. It is required

by the National Fuel Gas Code that a drip line be installed near the gas inlet. This should consist of a vertical length of pipe tee connected into the gas line that is capped on the bottom in which condensation and foreign particles may collect.

Figure 2

Method of Installing a Tee Fitting Sediment Trap (Figure 2) The use of the following gas connectors is recommended:

ANS Z21.24 Appliance Connectors of Corrugated Metal Tub- ing and Fittings

ANS Z21.45 Assembled Flexible Appliance Connectors of Other Than All-Metal Construction

The above connectors may be used if acceptable by the authority having jurisdiction. The state of Massachusetts requires that a flex- ible appliance connector cannot exceed three feet in length.

Pressure Testing of the Gas Supply System

1.To check the inlet pressure to the gas valve, a 1/8" (3mm) N.P.T. plugged tapping, accessible for test gauge connection, must be placed immediately upstream of the gas supply connection to the appliance.

2.The appliance and its appliance main gas valve must be discon- nected from the gas supply piping system during any pressure testing of that system at test pressures in excess of 1/2 psig (3.5 kPa).

3.The appliance must be isolated from the gas supply piping sys- tem by closing its equipment shutoff valve during any pressure testing of the gas supply piping system at test pressures equal to or less than 1/2 psig (3.5 kPa).

Attention! If one of the above procedures results in pressures in excess of 1/2 psig (14" w.c.) (3.5 kPa) on the appliance gas valve, it will result in a hazardous condition.

Checking Manifold Pressure

Natural gas will have a manifold pressure of approximately 3.5" w.c. (.87kPa) at the pressure regulator outlet with the inlet pressure to the pressure regulator from a minimum of 5.0" w.c. (1.245kPa) for the purpose of input adjustment to a maximum of 10.5" w.c. (2.615kPa). Propane/LP gas will have a manifold pressure ap- proximately 10.0" w.c. (2.49kPa) at the pressure regulator outlet with the inlet pressure to the pressure regulator from a minimum of 11.0" w.c. (2.739kPa) for the purpose of input adjustment to a maximum of 13.0" w.c. (3.237kPa).

A test gage connection is located downstream of the gas appliance pressure regulator for measuring gas pressure. The connection is a 1/8 inch (3mm) N.P.T. plugged tapping.

16943-7-0907

Page 7

Image 7
Contents Installation Instructions Table of Contents This is a Heating Appliance Important Safety InformationLP-GAS Warning Odor Safety Information for Users of LP-GASIntroduction SpecificationsUnusually Tight Construction Water Vapor a BY-PRODUCT of Unvented Room HeatersGAS Supply Clearances Optional Floor Stand InstallationSRS-18* and SRS-30 Floor Stand Installation Installation on Rugs and TileBF-10 and BF-20 On Sheet Rock Wall Wall Mount InstallationLighting Instructions For Your Safety Read Before LightingPiezo Pilot Ignitor Instructions Main Burner Flame CharacteristicsAir Shutter Adjustment Figure Cleaning Main Burner Orifice and Main BurnerBF-10 Pilot Flame CharacteristicsThermostat Operation Oxygen Depletion Sensor Pilot FigureAppliance Maintenance HOW to Order Repair Parts TroubleshootingParts List Parts View Excessive Blower Wheel Noise Optional Blower Installation InstructionsOptional Blower Installation Instructions Service Notes
Related manuals
Manual 20 pages 33.69 Kb