Desa CHDV32NR, (V)T32P Snorkel Termination Installation, Venting with Two 90 Elbows

Page 11

Venting Installation instructions

Continued

SNORKEL TERMINATION INSTALLATION

Recommended Applications:

• Installations requiring a vertical rise on building exterior

• Any installation using snorkel termination to achieve one foot above ground

Snorkel terminations are available for installations requiring a vertical rise on the exterior of the building. If installing snorkel termina- tion below grade, you must provide proper drainage to prevent water from entering snorkel termination (see Figure 16). Do not back fill around snorkel termination.

Snorkel Termination

Snorkel

Termination

12"

Minimum

Snorkel

 

Wall

Termination

 

 

Firestop

 

90° Elbow

 

 

12"

Minimum 45° Elbow

Adequate

Drainage

12"

Minimum

Figure 16 - Snorkel Termination Configurations for Below Ground Installation

HORIZONTAL SYSTEM INSTALLATION USING TWO 90° ELBOWS

The following configurations show the minimum vertical rise requirements for a horizontal system using two 90° elbows.

Venting with Two 90° Elbows

Vertical (V)

Horizontal

Horizontal (H1) +

 

(H1)

Horizontal (H2)

5' min.

2' max.

6' max.

6' min.

4' max.

12' max.

7' min.

6' max.

18' max.

8' min.

8' max.

20' max.

20' max.

8' max.

20' max.

45° Elbow

Venting with Two 90° Elbows

Vertical (V) Horizontal (H1)

 

Horizontal (H2) 45° Elbow

5' min.

6' max.

6' min.

12' max.

7' min.

18' max.

8' min.

20' max.

20' max.

20' max.

Figure 18 - Horizontal Termination Configuration for Venting Using Two 90° Elbows with Termination at 90° with Fireplace

Figure 17 - Horizontal Termination Configuration for Venting

Using Two 90° Elbows

108661-01F

www.desatech.com

11

Image 11
Contents What to do if YOU Smell GAS For Your SafetySafety Information Table of ContentsProduct Identification Local Codes Product FeaturesClearances Pre-Installation PreparationLocation and space requirements 23 1 Framing and finishingTermination CAP AIR Supply Inlet GAS Meter Location of Termination CapHorizontal Termination Installation Venting Installation InstructionsInstallation Precautions Installation PlanningVent Pipe Connections Installing Siding Standoff Square Termination Horizontal Termination ConfigurationsVenting with Two 90 Elbows Snorkel Termination InstallationOffset with Wall Strap and 45 Elbows Flat Ceiling InstallationVertical Venting Vertical Termination ConfigurationsInstalling optional blower accessories Fireplace InstallationHigh Altitude Installation Parts lists for venting kits and componentsBlower Model BK Model BKT InstallationInstallation Items Needed Installing Gas Piping to Fireplace LocationBlower Wiring Diagram Installation Items Needed Connecting Fireplace to GAS SupplyTest Pressures In Excess Of 1/2 Psig 3.5 kPa Pressure Testing Gas Supply Piping SystemPressure Testing Fireplace Gas Connections Checking GAS ConnectionsAttaching Alkaline Battery to Receiver Installing Remote ReceiverRemoving Glass Door Cleaning Glass DoorRemoving/Replacing Glass Door Removing Louver PanelsInstalling Log No Installing logs, lava rock and glowing embersInstalling Logs No and No Lighting Instructions For your safety read Before lightingManual Lighting Procedure Operating FireplaceOn/Off Series Model HRC100 OpTIONAL Hand-HeldRemote Operation Thermostat Series Model HRC200Operating optional GWMT1 Wall Mounted Thermostat Operating optional blower accessoryPilot assembly Inspecting BurnersLogs Cleaning MaintenanceGlass Door Pilot and burnersTo clean pilot. This can damage pilot unit TroubleshootingTroubleshooting Above Gas leak. See Warning statementSpecifications Replacement PartsService Hints Technical ServiceAccessories CHDV32NR Illustrated Parts BreakdownParts List CTDV36NR Parts List Keep this Warrant Warranty Information