NV360/580 Series
Framing and Finishing
Check appliance to make sure it is levelled and properly positioned.
1.Choose unit location.
2.Nailing flanges are supplied with the fireplace (found on the fireplace hearth). To level the box and secure it firmly in place, remove the nailing flanges from the hearth and install at the sides of the firebox as shown in Figure 3.
3.Screw through the slotted holes in the drywall strip and into
| C | Adjustable Drywall Strip | |
|
| ||
| A | (Nailing Flanges) | |
| B | Screw | Drywall |
|
| Position | Depths |
|
| A | 1/2" / 13 mm |
|
| B | 5/8" / 16 mm |
|
| C | 3/4" / 19 mm |
|
| Adjustable | |
|
| 1/2", 5/8" & 3/4" | |
|
| Spacing | |
|
|
| FP1023 |
Fig. 3 | Nailing flanges. |
|
|
Finishing
Noncombustible materials such as brick and tile can be extended over the face of the unit (Do not cover the glass door or grille). If a trim kit is to be installed, brick and tile will have to be installed flush with the side of this appliance.
Gas Specifications
|
|
| Max. | Min. |
Model | Fuel | Gas Control | Input | Input |
NV360RN | Natural | Millivolt Hi/Lo | 33,500 | 23,500 |
NV360RP | Propane | Millivolt Hi/Lo | 33,500 | 23,700 |
NV580RN | Natural | Millivolt Hi/Lo | 45,000 | 31,500 |
NV580RP | Propane | Millivolt Hi/Lo | 45,000 | 31,900 |
6
Air Shutter Setting
Model | Front | Rear |
NV360RN | closed | closed |
NV360RP | open | open |
NV580RN | closed | closed |
NV580RP | open | open |
Gas Inlet & Manifold Pressures
| Natural | LP |
|
|
|
Minimum Inlet Pressure | 5.5" w.c. | 11" w.c. |
Maximum Inlet Pressure | 14.0" w.c. | 14.0" w.c. |
Manifold Pressure | 3.5" w.c. | 11" w.c. |
|
|
|
NV360 / NV580
Certified to
ANSI
Vented Gas Fireplace
Units: H31A00, H31B00, I31A00, I31B00
High Elevations
Input ratings are shown in BTU per hour and are certified without deration for elevations up to 4,500 feet (1,370m) above sea level.
For elevations above 4,500 feet (1,370m) in USA, installations must be in accordance with the current ANSI Z223.1/NFPA 54 and/or local codes having jurisdiction.
In Canada, please consult provincial and/or local authorities having jurisdiction for installations at elevations above 4,500 feet (1,370m).
Gas Line Installation
When purging gas line the front glass must be removed.
The gas pipeline can be brought in through the right side of the appliance. Knockouts are provided at conve- nient locations to allow for the gas pipe installation and testing of any gas connection.
The gas line connection can be made with properly tinned 3/8” copper tubing, 1/2” rigid pipe or an approved flex connector. Since some municipalities have addi- tional local codes, it is always best to consult your local authority and the
For USA installations consult the current National Fuel Gas Code, ANSI Z223.1/NFPA 54.
Always check for gas leaks with a mild soap and water solution applied with a brush no larger than 1” (25 mm). Never apply soap and water solution with a spray bottle. Do not use an open flame for leak
testing.
20003565