Weil-McLain CGI-4E manual BOILER-bypass piping method, Valve adjustment

Page 26

GOLD CGi-4E Gas-Fired Water Boiler — Boiler Manual

4d Piping — low temperature systems

BOILER-bypass piping method

This piping method (Figure 22 or 23) is called a boiler- bypass because part of the circulator flow is bypassed around the boiler (through valve 7a). This method reduces the flow rate throughout the boiler, in order to raise the average water temperature in the boiler enough to prevent flue gas condensation. Boiler-bypass piping is effective for some boilers — including the CGi-4Eprovided the flow rates are adjusted according to the instructions following.

Figures 22 and 23 are alternative piping suggestions for converted gravity (large water content or steam systems) or radiant heating system — for use when primary/secondary piping can’t be applied. (Figure 24 is another alternative, using system bypass in place of boiler-bypass piping. Figure 24 however, is not suitable for radiant heating applications because it does not protect the radiant system from possible high water temperature.)

Boiler-bypass piping keeps system flow rate as high as possible and temperature drop as low as possible, help- ing to equalize the building heat distribution.

Temperature gauges

Gauge 4a is optional if the bypass valves will be ad-

justed using cold (or room temperature) return water to the boiler. (When setting the valves without gauge 4a installed — using cold or room temperature water

assume the return water temperature to be 60°F. Set the valves so gauge 8 reads at least 120°F.

Gauge 4b is optional on converted gravity systems, but required on radiant heating systems — to display the water temperature being supplied to the radiant tubing.

Gauge 8 is required on all systems to assure reliable adjustment of the bypass valves. The boiler-mounted temperature/pressure gauge can be used if a separate temperature gauge is not installed.

Valve adjustment

1.Start with valve 7a fully closed and 7b fully open.

2.Gradually open valve 7a while closing valve 7b until the temperature at gauge 8 reads 60 °F higher than gauge 4a. A minimum 60°F temperature rise through the boiler assures a low enough flow rate and high enough average temperature to prevent condensation even with low system return water temperature.

3.Valve 7a regulates the system flow rate, while valve 7b regulates the boiler flow rate.

4.The boiler-mounted temperature/pressure gauge may be used in place of a separate gauge 8.

Failure to prevent low return water temperature to the boiler could cause corrosion of the boiler sections or burners, resulting in severe personal injury, death or substantial property damage.

Radiant heating system piping should include a means of regulating the boiler return water temperature and the system supply temperature (such as provided by an injec- tion pumping control).

Boiler return water temperature will be adequately controlled using the methods shown

in this manual provided the system supply temperature is relatively constant.

DO NOT apply the methods of this manual if the system is equipped with an outdoor reset control. Instead, provide controls and piping which can regulate the boiler re- turn water temperature at no less than 130°F regardless of system supply temperature. Contact your Weil-McLain representative for suggested piping and control methods.

Failure to prevent cold return water temperature to the boiler could cause corrosion damage to the sections or burners, resulting in possible severe personal injury, death or substantial property damage.

26

Part Number 550-110-711/1108

 

Image 26
Contents GOLDCGi-4E How it works Gold CGi-4EGas-Fired Induced-Draft Water Boiler Contents Please read before proceeding Before locating the boiler, check the following 1a Prepare boiler location codes & checklistInstallations must follow these codes Check for nearby connection to1b Prepare boiler location clearances Chimney or vent require- ments When removing boiler from an existing common vent system1c Prepare boiler location vent system Products to avoid 1d Prepare boiler location air contaminationRemove contaminants permanently Areas likely to have contaminantsAir opening options 1e Prepare boiler location air openingsAir openings must be provided Two openings Air supply from inside the buildingSingle air opening option Exhaust fans and air moversMotorized air dampers Exception for large spacesPlace boiler/crate near position 2a Prepare boiler placement & setupOrifice replacement procedure Inspect orifices and burnersDrain and remove fittings 2b Prepare boiler pressure testHydrostatic pressure test Prepare boiler for testCGi-4E venting methods Chimney draft or Direct exhaust 3a Venting general informationVenting chimney draft venting Chimney draft ventingDo not exceed data in Table 3c Venting Direct exhaust componentsObtain vent system components Do not mix components3d Venting direct exhaust vent starter 3e Venting direct exhaust termination Do not wrap or insulate vent pipe or fittingsDo not mix types or manufacturers of vent materi- als 3f Venting direct exhaust installationSlip connector for Saf-T Vent Use their specified sealant. Do not use screwsUsing any termination other than one of those shown 4a Water piping general information Closed-type expansion tank 4b Water piping single-zone systemDiaphragm-type or bladder- type expansion tank Figure 4c Water piping multiple zones Piping multiple zonesBoiler isolation balancing valves System or zone circulator Zone valve Drain valveValve adjustment 4d Piping low temperature systemsTemperature gauges Primary/secondary preferred bypass piping methodBlend temperature gauge Valve adjustment BOILER-bypass piping methodBoiler-bypass piping Zoning with SYSTEM-bypass piping method System or zone circulator 4e Water piping refrigeration systemPrevent chilled water from entering boiler Chilled medium from entering boiler. See forNatural Gas Connecting gas supply piping to boilerGas piping Propane GasWiring connections Field wiringElectrical installation must comply with ThermostatCheck for gas leaks Freeze protection when used7a Start-up preparation Determine if water treatment is neededInspect base insulation Fill the system with waterInspect system water piping Close manual and automatic air vents and boiler drain cockCheck system and boiler 7b Start-up operate boilerStart the boiler Main burner flame Figure Check burner flamesPilot burner flame Figure Check for High limit switch set below boiler water tempera- ture?7c Start-up if boiler doesn’t start Gas not turned on at meter or boiler?Check-out procedure checklist 9a Operation sequence Boiler is now in the off cycleGold CGi-4E Gas-Fired Water Boiler Boiler Manual 9b Operation wiring diagrams Wiring diagramOperating instructions CMR 5.082a 1 through Addendum Instruction for Commonwealth of MassachusettsOne-half 1/2 inch in size, GAS Vent Directly be CMR 5.082a1 through10a Service and maintenance schedule Verify Proper Operation After Servicing10b Service and maintenance annual start-up Condensate drain system 10b Service & maintenance annual start-upBurners and base Inducer motorAir vents and air elimination Gas pipingCold fill and operating pressures Limit controls and cutoffsBoiler relief valve Safety relief valves should be reinspected AT LeastReview with owner Shut down boilerAir pressure switch 11a Troubleshooting generalBefore troubleshooting Check the following11b Troubleshooting components Control moduleControl module connections 11c Troubleshooting control module lights Chart 1 Troubleshooting Power light statusChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Chart 4 Flame & Power lights flashing Does blower motor operate? Item 8 , Verify Sequence of operation, , 12a Replacement parts Section assembly Base Jacket Trim Controls12b Replacement parts section assembly Description Weil-McLain Number Part number12c Replacement parts base Base assemblyDescription Weil-McLain Part number 12d Replacement parts jacket Jacket assemblyBoiler 12e Replacement parts trim Part number12f Replacement parts controls Propane gas components13a Dimensions Width13b Ratings DOEBreathing Fresh air Handling ceramic fiber and fiberglass materialsUse Niosh certified dust respirator N95

CGI-4E specifications

The Weil-McLain CGI-4E is a standout in the realm of commercial boilers, designed to meet the rigorous demands of a variety of heating applications. This gas-fired cast iron boiler exemplifies durability, efficiency, and performance, making it a popular choice in various commercial settings, including schools, hospitals, and office buildings.

One of the main features of the CGI-4E is its cast iron construction. Cast iron has long been favored for its excellent heat retention and distribution capabilities, leading to improved overall efficiency. The boiler is designed to maximize heat output while minimizing energy consumption. This characteristic is especially beneficial for businesses seeking to lower their energy costs without sacrificing comfort.

In terms of efficiency, the Weil-McLain CGI-4E boasts an impressive thermal efficiency rating. Its design incorporates advanced technology, allowing it to achieve an AFUE rating of up to 84%. This efficiency is achieved through features such as a full-modulating burner and a unique heat exchanger design that allows for optimal heat transfer and reduced flue gas temperatures.

The CGI-4E is also remarkable for its versatility. It is offered in a variety of sizes, making it suitable for different heating loads. This flexibility allows for installation in a wide range of environments, adapting easily to both existing and new heating systems. Additionally, the boiler comes with multiple venting options, including direct vent and conventional venting, further enhancing its installation flexibility.

Another standout feature is the integrated boiler control system, which simplifies operation and monitoring. This control system optimizes burner performance and enhances safety features, including automatic shut-off in case of system anomalies. The advanced controls also allow for easy integration with building management systems, enabling better energy management and reduced operational costs.

The CGI-4E also emphasizes ease of maintenance, with service-friendly designs that allow technicians to access components without difficulty. This consideration translates to reduced downtime and lower maintenance costs, ensuring that the boiler operates efficiently over its lifetime.

Overall, the Weil-McLain CGI-4E blends reliability, efficiency, and advanced technology, making it a premier choice for commercial heating needs. Its cast iron construction, impressive efficiency ratings, versatile installation options, and user-friendly controls solidify its reputation as a leading boiler solution in the industry.