Weil-McLain CGI-4E manual 11c Troubleshooting control module lights

Page 51

GOLD CGi-4E Gas-Fired Water Boiler — Boiler Manual

11c Troubleshooting — control module lights

CHART 1 — Troubleshooting POWER light status

— Usually indicates reversed 120 VAC polarity if POWER light flashes by itself —

Electrical shock hazard — Wherever you see TURN OFF POWER, follow the instructions. Failure to follow instructions could result in severe personal injury, death or substantial property damage.

Is POWER light off?

No

 

 

Yes

 

 

 

 

 

 

 

 

 

 

 

 

Is POWER light ...

 

 

 

 

 

 

Flashing

Flashing with

On steady

alone

another light

(not flashing)

 

 

 

 

 

 

 

 

 

 

 

 

 

TSTAT CIRC

Chart

 

 

 

light flashing

2

 

 

 

 

 

 

 

 

 

 

 

 

PRESS SWITCH

Chart

Chart

 

light flashing

3

5

 

 

 

 

 

 

 

FLAME

Chart

Chart

 

light flashing

4

6

 

 

 

 

 

 

For insufficient heat or no heat problem, go to Chart 7 if POWER light is on steady, with no other light flashing.

Make sure service switch or circuit breaker is on or fuses are good.

Remove 120 VAC IN plug (Figure 38, Item 3, page 50) on control module.

Using voltmeter, check across top and bottom pins of

120 VAC IN plug.

Does voltmeter indicate 120 VAC?

No

Yes

Problem is with incoming electricity. Have licensed electrician repair circuit.

Reconnect 120 VAC IN plug.

Remove 120 VAC IN transformer PRIMARY plug (Figure 38, Item 2, page 50) on control module.

Using voltmeter, check across top and bottom pins of

PRIMARY receptacle.

Does voltmeter indicate 120 VAC?

No

Yes

Usually indicates polarity on incoming 120 VAC power line is wrong.

TURN OFF POWER at service switch or breaker, then reverse the HOT and NEUTRAL wires entering the boiler in the J-box.

Restore POWER at service switch or breaker.

Is POWER light flashing now?

No

Yes

 

 

 

 

 

Have system checked by a

 

 

licensed electrician. If

 

 

problem persists, call your

Boiler should now

 

local Weil-McLain sales

operate normally.

 

representative.

 

 

 

Replace control module.

Retest.

Reinstall 120 VAC transformer PRIMARY plug.

Remove 24 VAC transformer plug (Figure 38, Item 5, page 50) on control module.

Using voltmeter, check pins of plug.

Does voltmeter indicate 24 VAC?

No

 

Yes

 

 

 

 

 

 

 

 

 

 

Replace transformer.

 

 

 

Retest and check for back

 

 

 

feed of voltage from

 

Replace control module.

system wiring.

 

Retest.

Part Number 550-110-711/1108

51

 

Image 51
Contents GOLDCGi-4E How it works Gold CGi-4EGas-Fired Induced-Draft Water Boiler Contents Please read before proceeding Check for nearby connection to 1a Prepare boiler location codes & checklistInstallations must follow these codes Before locating the boiler, check the following1b Prepare boiler location clearances When removing boiler from an existing common vent system 1c Prepare boiler location vent systemChimney or vent require- ments Areas likely to have contaminants 1d Prepare boiler location air contaminationRemove contaminants permanently Products to avoidTwo openings Air supply from inside the building 1e Prepare boiler location air openingsAir openings must be provided Air opening optionsException for large spaces Exhaust fans and air moversMotorized air dampers Single air opening optionInspect orifices and burners 2a Prepare boiler placement & setupOrifice replacement procedure Place boiler/crate near positionPrepare boiler for test 2b Prepare boiler pressure testHydrostatic pressure test Drain and remove fittingsChimney draft venting 3a Venting general informationVenting chimney draft venting CGi-4E venting methods Chimney draft or Direct exhaustDo not mix components 3c Venting Direct exhaust componentsObtain vent system components Do not exceed data in Table3d Venting direct exhaust vent starter Do not wrap or insulate vent pipe or fittings 3e Venting direct exhaust terminationUse their specified sealant. Do not use screws 3f Venting direct exhaust installationSlip connector for Saf-T Vent Do not mix types or manufacturers of vent materi- alsUsing any termination other than one of those shown 4a Water piping general information 4b Water piping single-zone system Diaphragm-type or bladder- type expansion tank FigureClosed-type expansion tank Piping multiple zones 4c Water piping multiple zonesSystem or zone circulator Zone valve Drain valve Boiler isolation balancing valvesPrimary/secondary preferred bypass piping method 4d Piping low temperature systemsTemperature gauges Valve adjustmentBlend temperature gauge BOILER-bypass piping method Valve adjustmentBoiler-bypass piping Zoning with SYSTEM-bypass piping method Chilled medium from entering boiler. See for 4e Water piping refrigeration systemPrevent chilled water from entering boiler System or zone circulatorPropane Gas Connecting gas supply piping to boilerGas piping Natural GasThermostat Field wiringElectrical installation must comply with Wiring connectionsDetermine if water treatment is needed Freeze protection when used7a Start-up preparation Check for gas leaksClose manual and automatic air vents and boiler drain cock Fill the system with waterInspect system water piping Inspect base insulation7b Start-up operate boiler Start the boilerCheck system and boiler Check burner flames Pilot burner flame FigureMain burner flame Figure Gas not turned on at meter or boiler? High limit switch set below boiler water tempera- ture?7c Start-up if boiler doesn’t start Check forCheck-out procedure checklist Boiler is now in the off cycle 9a Operation sequenceGold CGi-4E Gas-Fired Water Boiler Boiler Manual Wiring diagram 9b Operation wiring diagramsOperating instructions CMR 5.082a1 through Addendum Instruction for Commonwealth of MassachusettsOne-half 1/2 inch in size, GAS Vent Directly be CMR 5.082a 1 throughVerify Proper Operation After Servicing 10a Service and maintenance schedule10b Service and maintenance annual start-up Inducer motor 10b Service & maintenance annual start-upBurners and base Condensate drain systemLimit controls and cutoffs Gas pipingCold fill and operating pressures Air vents and air eliminationShut down boiler Safety relief valves should be reinspected AT LeastReview with owner Boiler relief valveCheck the following 11a Troubleshooting generalBefore troubleshooting Air pressure switchControl module 11b Troubleshooting componentsControl module connections Chart 1 Troubleshooting Power light status 11c Troubleshooting control module lightsChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Chart 4 Flame & Power lights flashing Does blower motor operate? Item 8 , Verify Sequence of operation, , Section assembly Base Jacket Trim Controls 12a Replacement partsDescription Weil-McLain Number Part number 12b Replacement parts section assemblyBase assembly 12c Replacement parts baseDescription Weil-McLain Part number Jacket assembly 12d Replacement parts jacketBoiler Part number 12e Replacement parts trimPropane gas components 12f Replacement parts controlsWidth 13a DimensionsDOE 13b RatingsHandling ceramic fiber and fiberglass materials Use Niosh certified dust respirator N95Breathing Fresh air

CGI-4E specifications

The Weil-McLain CGI-4E is a standout in the realm of commercial boilers, designed to meet the rigorous demands of a variety of heating applications. This gas-fired cast iron boiler exemplifies durability, efficiency, and performance, making it a popular choice in various commercial settings, including schools, hospitals, and office buildings.

One of the main features of the CGI-4E is its cast iron construction. Cast iron has long been favored for its excellent heat retention and distribution capabilities, leading to improved overall efficiency. The boiler is designed to maximize heat output while minimizing energy consumption. This characteristic is especially beneficial for businesses seeking to lower their energy costs without sacrificing comfort.

In terms of efficiency, the Weil-McLain CGI-4E boasts an impressive thermal efficiency rating. Its design incorporates advanced technology, allowing it to achieve an AFUE rating of up to 84%. This efficiency is achieved through features such as a full-modulating burner and a unique heat exchanger design that allows for optimal heat transfer and reduced flue gas temperatures.

The CGI-4E is also remarkable for its versatility. It is offered in a variety of sizes, making it suitable for different heating loads. This flexibility allows for installation in a wide range of environments, adapting easily to both existing and new heating systems. Additionally, the boiler comes with multiple venting options, including direct vent and conventional venting, further enhancing its installation flexibility.

Another standout feature is the integrated boiler control system, which simplifies operation and monitoring. This control system optimizes burner performance and enhances safety features, including automatic shut-off in case of system anomalies. The advanced controls also allow for easy integration with building management systems, enabling better energy management and reduced operational costs.

The CGI-4E also emphasizes ease of maintenance, with service-friendly designs that allow technicians to access components without difficulty. This consideration translates to reduced downtime and lower maintenance costs, ensuring that the boiler operates efficiently over its lifetime.

Overall, the Weil-McLain CGI-4E blends reliability, efficiency, and advanced technology, making it a premier choice for commercial heating needs. Its cast iron construction, impressive efficiency ratings, versatile installation options, and user-friendly controls solidify its reputation as a leading boiler solution in the industry.