Ultra electronic 105 Check for gas leaks Final checks before starting boiler, To start the boiler

Page 24

6 GAS-FIRED WATER BOILER SERIES 2 — Boiler Manual

Startup (continued)

Check for gas leaks

Final checks before starting boiler

Before starting the boiler, and during initial operation, smell near the floor and around the boiler for gas odorant or any unusual odor. Remove boiler front door and smell interior of boiler enclosure. Do not proceed with startup if there is any indication of a gas leak. Repair any leak at once.

DO NOT adjust or attempt to measure gas valve outlet pressure. The gas valve is factory-set for the correct outlet pressure. This setting is suitable for natural gas and propane, requiring no field adjustment. Attempting to alter or measure the gas valve outlet pressure could result in damage to the valve, causing potential severe personal injury, death or substantial property damage.

Propane boilers only — Your propane supplier mixes an odorant with the propane to make its presence detectable. In some instances, the odorant can fade, and the gas may no longer have an odor. Before startup (and periodically thereafter), have the propane supplier verify the correct odorant level in the gas.

Check thermostat circuit(s)

1.Disconnect the two external wires connected to the boiler thermostat terminals (low voltage terminal strip terminals 5 and 6).

2.Connect a voltmeter across these two incoming wires. Close each thermostat, zone valve and relay in the external circuit one at a time and check the voltmeter reading across the incoming wires.

3.There should NEVER be a voltage reading.

4.If a voltage does occur under any condition, check and correct the external wiring. (This is a common problem when using 3-wire zone valves.)

5.Once the external thermostat circuit wiring is checked and corrected if necessary, reconnect the external thermostat circuit wires to boiler low voltage terminal strip terminals 5 and 6. Allow the boiler to cycle.

Inspect/fill condensate system

Inspect/check condensate lines and fittings

1.Inspect the condensate drain line, condensate PVC fittings and condensate trap. (See page 20 for component locations.)

2.Pour water into the top of the boiler’s ½" PVC condensate tee and check for any leaks in the condensate drain line or fittings. Repair any leaks.

Fill condensate trap with water

1.Loosen the hose clamp securing the right end of the condensate trap to the PVC reducing elbow (see page 20).

2.Slide the trap hose end off of the elbow.

3.Fill the trap with fresh water to within a inch of the end of the hose.

4.Replace trap hose on PVC reducing elbow and tighten the hose clamp.

The condensate trap (page 3, item 23a) must be filled with water during all times of boiler operation to avoid flue gas emission from the condensate drain line. Failure to fill the trap could result in severe personal injury or death.

Read the Ultra Control Supplement to familiarize yourself with Ultra PhD control module operation. Read Operating Instructions in Control Supplement for proper steps to start boiler.

Verify the boiler and system are full of water and all system components are correctly set for operation.

Verify the preparation procedures of section 6, pages 23 and 24 have been completed.

Fill vent condensate trap with water (by removing hose clamp and hose at PVC reducing elbow). Replace hose on PVC reducing elbow and tighten clamp.

Verify electrical connections are correct and securely attached.

Inspect vent piping and air piping for signs of deterioration from corrosion, physical damage or sagging.Verify air piping and vent piping are intact and correctly installed per Ultra Boiler Vent Supplement.

To start the boiler

1.Turn OFF Power switch on Ultra display panel. Turn on power to boiler.

2.Read and follow the Operating Instructions in the Ultra Control Supplement.

If boiler does not start correctly

1.Check for loose connections, blown fuse or service switch off?

2.Is external limit control (if used) open? Is boiler water temperature above 200 °F?

3.Is thermostat set below room temperature?

4.Is gas turned on at meter or boiler?

5.Is incoming gas pressure less than 4" w.c. for natural gas or 5” w.c. for propane?

6.Are parameters set correctly as instructed in the Ultra Control Supplement?

If none of the above corrects the problem, refer to Troubleshooting in the Ultra Control Supplement.

24

Part number 550-100-026/0404

Image 24
Contents Gas-fired Water boiler Series Series 1/Series 2 identificationBOILER, with PhD Technology HOW IT Works GAS-FIRED Water BOILER, with PhD Technology Contents Hazard definitionsWhen servicing boiler Please read before proceedingBoiler operation Boiler waterInstallations must comply with Prepare boiler locationBefore locating the boiler, check Provide clearancesResidential garage installation Flooring and foundationProvide air openings to room Vent and air pipingWhen removing a boiler from existing common vent system Prevent combustion air contaminationSeal any unused openings in the common venting system Prepare boiler Remove boiler from crateUltra-80 Series 1 and 2 only Propane operation Ultra-310 Series 1 Boilers only Propane operationPlacing floor-mounted boilers Placing wall-mounted boilersSet boiler in place and check level Perform hydrostatic pressure test Prepare boiler for testFill and pressure test Drain and remove fittingsInstall water piping Install relief valveAdditional controls, when required General piping informationSystem water piping methods CirculatorsSizing space heat system piping Sizing DHW system piping Required boiler water flow rate, GPM, at 180FZoning with zone valves Connect boiler to system as shown in whenControlling the system circulator Zoning with circulators Setting boiler outlet water target temperature Radiant heating applicationsChilled water systems Chilled water system plus optionalInstall vent and combustion air piping Venting, combustion air & condensate linePrepare condensate fittings Connect condensate drain Leave the top of the ½ tee OPEN. This is needed as aVacuum break Connecting gas supply piping Gas pipingWall-mounted boilers Natural Gas Propane GasPipe sizing for natural gas Natural gas supply pressure requirementsFreeze protection when used StartupCheck/control water chemistry Fill and test water systemCheck for gas leaks Final checks before starting boiler Check thermostat circuitsInspect/fill condensate system To start the boilerAdjust and test boiler controls Check system and boilerCheck flame & combustion Check-out/startup verification Check-out/startup verification Installation certificate Annual startup and general maintenance Service and maintenance schedulesAnnual startup Handling ceramic fiber materialsClean condensate trap Check water systemCheck all piping for leaks Check expansion tank Check air openingsCheck ignition ground wiring Check all boiler wiringCheck control settings Check boiler relief valveCheck flame signal Check flue gas temperaturePerform startup and checks Check burner flameMaintenance general General maintenanceCleaning boiler heat exchanger Replace boiler jacket front door after startup or servicingMaintenance and annual startup Access exchanger Ultra-155, -230, -310 OnlyExchanger cleaning ALL models Replacement parts Jacket parts Replacement parts Heat exchanger and piping Ultra-80 Replacement parts Heat exchanger and piping Ultra-155 to Replacement parts Controls Dimensions Ratings DOE

230 & -310, 105, 155, 80 specifications

Ultra Electronics, a recognized leader in advanced electronic systems, has developed various innovative products catering to different fields, particularly defense, aerospace, and security. Among its notable offerings are the Ultra 230 and demographic models such as the -310, -105, -155, and -80, each designed to meet specific operational requirements and challenges.

The Ultra 230 is renowned for its superior processing capabilities, which leverage high-performance computing to manage complex tasks efficiently. This platform integrates multifaceted technologies like electronic warfare, communications, and sensor data fusion, ensuring that users have real-time information for informed decision-making. The design emphasizes modularity, allowing end-users to customize the system according to their mission profiles.

The Ultra 310 variant extends the functionalities of the 230, providing enhanced connectivity options. Its robust communication interfaces facilitate seamless integration with various networks, ensuring effective data exchange across multiple platforms. This model is particularly effective in joint operations where interoperability is critical among allied forces.

Ultra's -105 model is designed specifically for ground vehicles, offering ruggedness and resilience under harsh conditions. It features advanced environmental protection, allowing it to withstand dust, moisture, and vibration. This makes the -105 ideal for tactical military applications where reliability in diverse terrains is crucial.

The -155 model emphasizes versatility and adaptability, boasting a wide range of components and configurations. This allows for easy upgrades and maintenance, enabling military and defense organizations to stay current with technological advancements without significant investments in new equipment.

Lastly, the Ultra 80 is aimed at the aviation sector, focusing on lightweight design without compromising on power or functionality. It employs cutting-edge materials that enhance performance while reducing overall weight, making it ideal for aerial applications.

In summary, Ultra Electronics' products - the 230, -310, -105, -155, and -80 - showcase a commitment to innovation and operational excellence. Each model brings forth unique features and technologies, ensuring they meet the diverse needs of their users across various industries. From advanced processing capabilities to rugged designs suitable for any environment, Ultra Electronics continues to push the boundaries of technological advancement, maintaining its position as a frontrunner in the electronic systems market.