State Industries 100, 101 warranty System Connections

Page 15

DISCONNECT THE APPLIANCE AND ITS MANUAL GAS SHUTOFF VALVE FROM THE GAS SUPPLY PIPING SYSTEM DURING ANY SUPPLY PRESSURE TESTING EXCEEDING 1/2 PSIG (3.45Kpa). GAS SUPPLY LINE MUST BE CAPPED WHEN DISCONNECTED FROM THE HEATER. FOR TEST PRESSURES OF 1/2 PSIG (3.45Kpa) OR LESS, THE APPLIANCE NEED NOT BE DISCONNECTED, BUT MUST BE ISOLATED FROM THE SUPPLY PRESSURE TEST BY CLOSING THE MANUAL GAS SHUTOFF VALVE.

BEFORE PLACING THE HEATER IN OPERATION, CHECK FOR GAS LEAKAGE. USE SOAP AND WATER SOLUTION OR OTHER MATERIAL ACCEPTABLE FOR THE PURPOSE OF LOCATING GAS LEAKS. DO NOT USE MATCHES, CANDLES, FLAME OR OTHER SOURCES OF IGNITION FOR THIS PURPOSE.

PURGING

Gas line purging is required with new piping or systems in which air has entered.

CAUTION

PURGING SHOULD BE PERFORMED BY PERSONS EXPERIENCED IN THIS TYPE OF GAS SERVICE. TO AVOID RISK OF FIRE OR EXPLOSION, PURGE DISCHARGE MUST NOT ENTER CONFINED AREAS OR SPACES WHERE IGNITION CAN OCCUR. THE AREA MUST BE WELL VENTILATED AND ALL SOURCES OF IGNITION MUST BE INACTIVATED OR REMOVED.

GAS METER SIZE - CITY GASES ONLY

Be sure that the gas meter has sufficient capacity to supply the full rated gas input of the water heater as well as the requirements of all other gas fired equipment supplied by the meter. If the gas meter is too small, ask the gas company to install a larger meter having adequate capacity.

GAS PRESSURE REGULATION

Main line gas pressure to the water heater should be between a maximum 10.5" (2.59Kpa) W.C. (14.0"/3.45Kpa for propane) and a minimum as shown in Table 4: that is, for Natural Gas, 4.8" (1.18Kpa) W.C. and 8.5" (2.08Kpa) for Propane Gas. The inlet gas pressure must not exceed the maximum value. A service regulator must be installed within 10' (305 cm) of unit.

WARNING

FAILURE TO INSTALL A PRESSURE REGULATOR WITHIN 10 FEET OF THE WATER HEATER CAN RESULT IN LEAKAGE OF FLUE GASES INTO THE SURROUNDING ROOM. SERIOUS PERSONAL INJURY OR DEATH COULD RESULT FROM INHALATION OF CARBON MONOXIDE GAS.

GAS VALVES

WARNING

SHOULD OVERHEATING OCCUR OR THE GAS SUPPLY FAIL TO SHUT OFF, TURN OFF THE MANUAL GAS CONTROL VALVE TO THE APPLIANCE.

SYSTEM CONNECTIONS

The system installation must conform to these instructions and to the local code authority having jurisdiction. Good practice requires that all heavy piping be supported.

RELIEF VALVE

This heater is equipped with an approved temperature and pressure relief valve. ASME ratings cover pressure relief. CSA ratings cover release rate with temperature actuation.

FOR SAFE OPERATION OF THE WATER HEATER, THE RELIEF VALVE(S) MUST NOT BE REMOVED OR PLUGGED.

In addition to the appliance relief valve, each remote storage tank which may be used in conjunction with this appliance shall also be installed with a properly sized, rated and approved temperature (ANSI) and pressure (ASME) relief valve(s). This relief valve shall comply with the standard for relief valves for hot water supply systems. ANSI Z21.22-CSA 4.4.

Your local code authority may have other specific relief valve requirements.

WARNING

THE PURPOSE OF A RELIEF VALVE IS TO AVOID EXCESSIVE PRESSURE OR TEMPERATURE INTO THE STEAM RANGE, WHICH MAY CAUSE SCALDING AT FIXTURES, TANK EXPLOSION, SYSTEM OR HEATER DAMAGE. NO VALVE IS TO BE PLACED BETWEEN THE RELIEF VALVE AND THE TANK.

A DRAIN LINE MUST BE CONNECTED TO THE RELIEF VALVE TO DIRECT DISCHARGE TO A SAFE LOCATION TO AVOID SCALDING OR WATER DAMAGE. THIS LINE MUST NOT BE REDUCED FROM THE SIZE OF THE VALVE OUTLET AND MUST NOT CONTAIN VALVES OR RESTRICTIONS, NOR SHOULD IT BE LOCATED IN FREEZING AREAS. DO NOT THREAD OR CAP THE END OF THIS LINE. RESTRICTED OR BLOCKED DISCHARGE WILL DEFEAT THE PURPOSE OF THE VALVE AND IS UNSAFE. THE DISCHARGE LINE SHALL BE INSTALLED TO ALLOW COMPLETE DRAINAGE OF BOTH THE VALVE AND LINE.

WATER LINE CONNECTIONS

This manual provides detailed installation diagrams (see back section of this manual) for typical methods of application for the water heaters.

The water heater may be installed by itself, or with a separate storage tank.

CLOSED SYSTEM

CAUTION

A closed system will exist if a check valve (without bypass), pressure reducing valve (without bypass), or a water meter (without bypass) is installed in the cold water line between the water heater and street main (or well).

Excessive pressure may develop causing premature tank failure or intermittent relief valve operation. This type of failure is not covered by the limited warranty. An expansion tank or a similar device may be required in the inlet supply line between the appliance and the meter or valve to compensate for the thermal expansion of water under supply pressure.

If a water heater is installed in a closed water system, check local codes or contact the water supplier or local plumbing inspector on how to control this situation.

THERMOMETERS (Not Supplied)

WATER (POTABLE) HEATING AND SPACE HEATING

Thermometers should be obtained and field installed as shown in the installation diagrams.

Thermometers are installed in the system as a means of detecting the temperature of the outlet water supply.

1.All piping components connected to this unit for space heating applications shall be suitable for use with potable water.

2.Toxic chemicals, such as those used for boiler treatment, shall

NEVER be introduced into this system.

15

Image 15
Contents Printed Ultra Force SUF 60 120 Thru SUF 100Ultra Force SUF 120 250A ROUGH-IN-DIMENSIONS Temperature Rise Degrees F Gallons PER HourForeword Features Table of ContentsInstallation Instructions Clearances Locating the HeaterUnconfined Space Hard WaterAIR Requirements Mechanical Exhausting of Room AIRBELOW. Keep Clear of ALL Obstructions Canadian Power Vent Power VentCanadian Direct Vent Direct VentDirect Vent Terminal Installation Installation SequenceDirect Venting Vertical Vent Terminal Installation Selection of Materials Installation of Vent SystemVent Pipe Preparation Initial PreparationGAS Piping Controls and SwitchesAttaching gas supply pipe to gas valve inlet Connection of GAS PipeSystem Connections Heater Wiring Overview Using the Electronic ControllerOperating States Changing the Display Units Prior to Start UP Viewing the Fault HistoryOperating Instructions Adjustment ProcedureGeneral Information MaintenanceFor Your Safety Read Before Operating Models only 199/250 Models only Sediment Removal Powered Anode SystemFlushing DrainingVent System Drain Valve and Access PanelsInstallation Diagrams Page Must be Identical Heaters Pipe Relief Valve to Open Drain Page Manifold Kits TROUBLE-SHOOTING Checklist and Service InformationGAS Fails to Shut OFF Replacement PartsMotor will not RUN Motor RUNS, Burner Lights Momentarily Then Locks OUTModel SUF Limited Warranty Page Page Page Tennessee Waltz Parkway Ashland CITY, TN

100, 101 specifications

State Industries 101,100 is an innovative company that specializes in manufacturing high-quality industrial equipment and machinery. Founded with a vision to enhance productivity and efficiency across various sectors, State Industries has established itself as a trusted name in the industry. The company is known for its commitment to quality, sustainability, and cutting-edge technology, making it a preferred choice for businesses looking to elevate their operations.

One of the main features of State Industries 101,100 is its extensive product line, which includes a wide range of industrial machines, tools, and systems. The company’s offerings are designed to cater to various industries, such as manufacturing, construction, energy, and transportation. From heavy-duty machinery to precision tools, State Industries ensures that its products meet the highest standards of performance and reliability.

A key aspect of State Industries’ success is its incorporation of advanced technologies in its manufacturing processes. The company utilizes state-of-the-art machinery and techniques, including computer-aided design (CAD), robotics, and automation. These technologies enable State Industries to produce parts and equipment with exceptional precision, which ultimately leads to improved overall performance. Additionally, the company places a strong emphasis on research and development, constantly seeking new ways to innovate and enhance its product offerings.

Sustainability is another defining characteristic of State Industries 101,100. The company is deeply committed to minimizing its environmental impact by adopting eco-friendly practices throughout its operations. This includes using sustainable materials, reducing waste during production, and implementing energy-efficient technologies. State Industries also actively engages in initiatives aimed at promoting green technology, striving to contribute positively to the environment while delivering high-quality industrial solutions.

Customer satisfaction remains a top priority for State Industries. The company fosters strong relationships with its clients by offering tailored solutions, responsive customer service, and comprehensive support throughout the product lifecycle. With a focus on understanding customer needs and challenges, State Industries is dedicated to delivering exceptional value and reliability with every product.

In summary, State Industries 101,100 stands out as a forward-thinking company that combines advanced technology, a commitment to sustainability, and a customer-centric approach in its operations. As industries evolve and face new challenges, State Industries is well-positioned to continue leading the way in industrial innovation.