AEG 8000038784_00_BAL_en user manual Troubleshooting, Event text Description Remedy

Page 22

4. Troubleshooting

4. Troubleshooting

4.1. Troubleshooting

Only trained and authorised personnel familiar with electrical systems and safety issues may work on inverters and electrical installations.

Should the inverter not supply energy as expected, go through the checklist before calling serv- ice.

1.Check that the grid is properly connected to the inverter and that the mains switch is not switched off.

2.Check that there is sufficient solar radiation to generate power. UPV >250 V

3.Check for shading and loose cables/connections in the PV system.

4.Check whether the voltage of the PV modules are within the expected values. If not go to point 7.

5.Check whether the voltage values of the grid lie within the threshold values. If this is not the case please contact your public utility for technical assistance.

6.If the above-mentioned points are OK, wait 15 minutes to find out whether there is a permanent failure.

7.If the PV system still supplies no power to the grid, check the display for:

4

-PV module voltage, current and power

-grid voltage, current and power

-event text, see log area

Then call service.

In the event of a failure, the red LED will flash and the display will show an event. Refer to the table for event descriptions and recommended actions.

Event text

Description

Remedy

Grid

Grid values are out of range

Check the voltage and frequency values in the display. If values

 

 

are zero, check the circuit-breaker (fuses) and cables. If values

 

 

are outside the applied limits, request technical service from in-

 

 

staller/energy company.

PV

The PV isolation resistance is too

Make a visual inspection of all PV cables and modules. If the event

 

low

occurs frequently, request technical service.

Internal

An internal event has occurred

Make sure airflow over the heat sink is not obstructed. Wait 5 mi-

 

 

nutes. If the inverter does not reconnect (although sufficient irra-

 

 

diance is available) or the event occurs regularly, action must be

 

 

taken. Service inverter.

Fail Safe

Internal or AC installation error

Turn off both AC and DC (PV) power to the inverter. Make a visual

 

 

inspection of the PV installation, if everything is in order, wait 5

 

 

minutes and re-apply AC and DC (PV) power. If the inverter re-

 

 

sumes fail safe operation, action must be taken. Service inverter.

Table 4.1: Events

Note:

For more event descriptions, refer to the Protect PV Reference Manual in the download area at: www.aegps.com/solarinverters

8000038784_00_BAL_en / L00410565-01_02

21

Image 22
Contents Protect PV Solar Inverters Contents Introduction Introduction Operation Mode DefinitionIntroduction Introduction Display DisplayView Menu Structure View Parameter DescriptionStatus Menu Structure Status Display Functions DescriptionDisplay Production Log Menu Structure Production Log Display Functions DescriptionDisplay Setup Menu Structure Setup Display Functions DescriptionDisplay Setup Sequence Access and Initial SetupAccess via PC Ethernet Interface Web Server Quick Guide7 Master setting Setup Wizard7 Display language 7 Installed power 7 Time and date7 Country setting 7 Replication Web Server Structure Operation7 Inverter startup Illustration 3.9 Overview Plant, Group and Inverter Views Additional Information Unit View DescriptionTroubleshooting TroubleshootingEvent text Description Remedy Cleaning the Cabinet MaintenanceMaintenance Cleaning the HeatsinkFrance & Africa Italy Czech Republic