U-Line 2015WCOL manual Other Site Requirements, Power Supply, Environmental Requirements

Page 6

2015WC/2015WCOL Wine Captain®

 

 

2.Remove plastic screw plugs (3 each, top and bottom) from new hinge location. Do not discard (see Figure 6).

7. With bottom of door facing up, remove pivot plate

(2 screws), flip over, and remount on opposite side of

door (see Figure 9). Be sure angled side of plate faces

center.

Figure 5

Screw Plugs

Figure 6

Figure 9

3.Remove top hinge (3 screws), reinstall hinge screw pin, and remount on opposite side BOTTOM (see Figure 7).

4.Remove the two door closer inserts from the existing bottom hinge and install as shown on the new bottom hinge (see Figure 8).

8.Holding door upright with top of door tilted forward, place hole of door pivot plate on bottom hinge screw pin (see Figure 10).

9. Tilt top of door into

position in top hinge and

install top hinge screw pin.

Hinge

Screw

Pin

Figure 7

Door

Closer

Inserts

Figure 8

10. Install plastic screw plugs

removed in Step 2 in old

hinge holes (3 each, top

and bottom).

Other Site Requirements

5.Remove existing bottom hinge (3 screws) and remount on opposite side TOP. Remove hinge screw pin.

6.Remove the plastic hole plug from the top of the door to allow the pivot pin to be inserted in the new location. Install the plug into the vacated hole on the opposite side.

Power Supply

The unit requires a grounded and polarized 115 VAC, 60 Hz, 15A circuit (normal household current). See Electrical Specifications on Page 13.

Environmental Requirements

The surrounding air temperature must be at least 50°F (10°C) but must not exceed 110°F (40°C). The unit must not be located near heat-generating equipment or in direct sunlight.

www.U-LineService.com

6

02/2005

Image 6
Contents 2015WC Wine Captain 2015WCOL Wine Captain with Overlay Contents Follow Safety PrecautionsTools/Materials Required General PrecautionsInspect and Plan InspectionExterior Cleaning Cut-Out DimensionsPrepare Site Product Dimensions Door Swing/Clearances InformationReversing the Door Power Supply Other Site RequirementsEnvironmental Requirements Side-By-Side Installation Instructions Adding a Final Finish Coat to Wood TrimPrepare Racks and Door Frame Staining Wood Trim a Different Color Overlay FrameFrame Preparation Typical routing dimensions are shown in Figure Installation Instructions Preparing DoorGo on to 5 Adjust Door Adjusting Door Alignment Adjust DoorChecking Door Alignment Electrical Specifications Leveling Information Installation TipPrepare Power Supply Level the Unit Anti-Tip Bracket Installation Install the UnitInstallation Troubleshooting Initial Start-Up Start-Up TroubleshootingStart-Up for the First Time Service Information Who to Call