BEFORE INSTALLING HOOD

ELELCTRICAL

Install a 1/2” conduit from the service panel long enough to reach the hood once it is installed.

Branch circuit requirement is 120V, 60Hz, 15A(minimum).

INFRARED LAMP AND PANEL KIT

Optional infrared lamp and panel kit can be ordered separately and mounted into your vent hood. Models available: IR30, IR36 and IR48. See instructions supplied with kit for assembly to your hood.

WARNING

To avoid any electrical shock the installation of the IR lamp should be done by a qualified electrician and before starting the installation of the hood.

DUCTING

Hood models: ES30, ES36, VS30, VS36 are supplied with a starting collar and backdraft damper on top

of the hood for connection to 8” round duct. Models: VS1236 and VS48 are supplied with a 10” round transition with damper and is assembled as shown in Fig. 3.

Vertical Discharge Figure

6"

canopy

Horizontal Discharge Figure

FIG. 1

A

FOR 900 ELBOW

A

canopy

10”16”

8”11”

FIG. 2

Install ducting long enough to reach the transition once the hood is installed plus 1-1/2 inch to connect ductwork.

ASSEMBLE TRANSITION TO HOOD (VS1236 and VS48 hoods only)

The transition supplied with the hood mounts to the top of the hood, Figure 3.

1.Place the transition piece over the hood exhaust and secure with 4 screws provided (Figure 3).

2.Duct tape connection between transition and hood.

3.Remove tape holding damper

FIG. 3

9

Image 11
Contents Professional and Euro Vent Hood Page Please Retain this Manual for Future Reference Message to OUR CustomersTable of Contents Safety Practices and Precautions To reduce the risk of a range top grease fire Safety Practices & PrecautionsSafety Practices & Precautions Wall Mount Venthhood Product Dimensions Euro Venthood Parts not Included with Your Hood PartsParts Included with Your Hood Vent unit to outside of building only Before Installing HoodTypical Installation Vertical Discharge Figure ElelctricalInfrared Lamp and Panel KIT DuctingHood Installation Height InstallationWall Mount Installation Hood Model Assembly and Installation Duct Covers Cabinet Preparation Cabinet InstallationES Series Wiring the Hood Integral Ventilator InstallationBefore YOU Call for Service HOW to Obtain ServiceThis Warranty does not Cover WarrantyLimited Warranty HOW Long does this Limited Warranty LAST?No Other Warranties HOW to GET ServiceCommercial USE Modèles Hotte DE Ventilation Série Professionnelle ET EuropéenneVeuillez Conserver CE Manuel À Titre DE Référence Lintention DE NOS ClientsAvertissement Avertissement Relatif À LA Sécurité Table DES MatièresMise EN Garde Mesures DE Sécurité ET DE PrécautionPour réduire les risques de feu de graisse sur la cuisinière Mesures DE Sécurité ET DE Précaution Hotte À Évacuation À Montage Mural Dimensions DU ProduitHotte À Évacuation Européenne Pièces NON Incluses Avec LA Hotte PiècesPièces Incluses Avec LA Hotte Installation Typique Avant Dinstaller LA HotteVerticale ElectricalLampe Infrarouge ET KIT DE Panneau ConduitsMontage Mural Modèle DE Hotte Hauteur dinstallation de la hotteMettez la hotte de niveau et serrez les vis dans la fente Assemblage ET Installation DES COUVRE-CONDUITSES30/ES36 Hotte DE Série VS30/VS36 Hotte DE Série Avant Dinstaller LA HotteImportant Fixez le moteur à la hotte Installation EN ArmoireInstallation DU Ventilateur Intégral Câblage DE LA Hotte Avertissement Câblage DE LA Hotte Avec UN Ventilateur IntégralAvant Dappeler LE Service Technique Pour Lobtention DE ServiceQuelle EST Durée DE Cette Garantie LIMITÉE? GarantieGarantie Limitée Fisher & Paykel Sengage ÀUtilisation Commerciale Pour Obtenir DES RéparationsAucune Autre Garantie Remarque Remarque