The actively redundant parallel operation automatically switches to
The connection normally takes place in the
9.2Set-up / Connection of Parallel Operation Board
The mains connection of each individual UPS takes place in the same way as described in chapter 5.
The
In UPS bypass mode, the phase L1 is used to connect the
The UPS outputs are each connected with the parallel operation busbar via an isolator. The instructions from chapter 5 apply here too.
The following always holds true for the UPS input and output conductors: The difference in length in conductors up to 20 m per UPS can be max. 20% and max. 10% for lengths > 20 m per UPS.
The jumper installed between “JP1” and “JP2” on the connection panel of every UPS at the factory must be removed. The UPS output distribution also has to take place according to the instructions in chapter 5. In particular, make sure that the individual switching elements are correctly labelled, in order to prevent operating errors later as well. The
52