2.If more headroom is needed when moving dryer into position, the top console (module) may be removed. a. To Remove Top Console (Module)

1)Disconnect the ground wire (A) at the rear of dryer.

2)Remove the six (6) sets of nuts and washers (B) holding the console (module) to base. (Located within control boxes.)

3)Open control door and control panel then disconnect the following:

a)On the right side box, disconnect the 4-pin plug as well as the 4-pin and 2-pin plug located on the microprocessor controller (computer). Additionally, remove the air connection at the union, and the two (2) ground wires connected to the dryer base.

b)On the left side box, disconnect the drive and blower motor wires, along with the 2-pin plug and the three (3) ground wires (two [2] that go to the panel and one [1] that goes to the dryer base).

4)Lift the console (module) off the dryer base (C).

IMPORTANT: The dryer must be transported and handled in an upright position at ALL times.