6 | HANDSHOWER INSTALLATION | 11 |
(FOR MODEL 7010.901 ONLY) | ||
| Drop SPRAY ESCUTCHEON (1) through the fourth hole of the tub ledge (12" max from SPOUT | 9 |
| center) with SPRAY ESCUTCHEON (1) directed towards tub center. Be sure RUBBER RING (2) |
|
| is properly seated in ESCUTCHEON (1). Install RUBBER WASHER (3) and LOCKNUT (4) from |
|
| underside of ledge. |
|
Secure SPRAY ESCUTCHEON (1) by tightening LOCKNUT (4).
Add SEAL WASHER (5) and connect HOSE (10) to outlet nipple |
|
| 6 | ||
at the bottom of TEE (7). Tighten firmly. |
|
|
| 1 | |
Slip SHOWER HOSE (8) with COUPLING NUT through SPRAY |
|
| |||
|
| 2 | |||
HOLDER (6) and ESCUTCHEON (1). ( Note: SPRAY HOLDER (6) |
|
| |||
must be separate from ESCUTCHEON (1) to get HOSE (8) |
|
| 3 | ||
thrrough ESCUTCHEON (1).] Install SEAL (9) and connect both | 7 |
|
| ||
HOSES (8) and (10). INSTALL second SEAL (9) and connect |
| 4 | |||
HAND SHOWER (11) to SPRAY HOSE (8). |
| 5 |
| ||
|
|
|
|
| |
|
|
|
| 10 | 8 |
| When not in use, HANDSHOWER should be seated |
|
|
| |
NOTE |
|
|
|
| |
in the HOLDER. |
|
|
| 9 | |
|
|
|
| ||
7 MAKE WATER SUPPLY CONNECTIONS |
|
|
| HAND | |
|
|
|
|
| SHOWER |
Connect HOT water supply to LEFT INLET | TRANSFER KNOB |
|
|
| |
UNION (1) and COLD water supply to |
|
|
| ||
|
|
|
| ||
RIGHT INLET UNION (2). Pipe connections |
|
|
|
| |
are 3/4" NPT. Use sealant or Teflon tape |
|
|
|
| |
on pipe connections. |
|
|
|
| |
Do not solder directly to valve body. |
|
|
|
|
7A TEST INSTALLED FAUCET
With HANDLES in OFF position, turn on WATER SUPPLIES and check all connections for leaks.
Operate both HANDLES to flush water lines thoroughly.
Lift HAND SHOWER from HOLDER, direct spray into tub. Lift TRANSFER KNOB to check HAND SHOWER and HOSES for leaks.
Turn handles "off" and replace HAND SHOWER.
HOT
1
3/4" NPT
COLD
2
3/4" NPT
3/4" X 3/4" NPT UNION (NOT SUPPLIED)
IMPORTANT: It is strongly recommended that access be provided for all enclosed mechanical parts to this system.
8 | Before the bathroom is completely finished, you may |
want to remove spout, handshower, and handles to | |
avoid damage during construction. |
To remove handles, reverse steps in section 4.
To remove SPOUT (1), proceed as follows:
Unthread LIFT ROD KNOB (2) to release it from the TRANSFER ROD (8). Remove LIFT ROD KNOB (2). VIEW A.
Remove PLUG BUTTON (3) and remove SET SCREW (4) using 4mm hex wrench supplied.
Lift SPOUT (1) off SHANK (5) carefully and remove RUBBER RING (6).
Unthread SHANK SLEEVE (7) and remove from SHANK (5).
Reverse sequence to
| 2 |
|
VIEW "A" |
| |
|
| 8 |
| 3 |
|
1 | 4 | FIG. 1 |
6 |
| |
| VIEW "A" | |
8 |
| |
Hex wench |
| |
| (supplied) |
|
7
5
CARE INSTRUCTIONS:
DO: SIMPLY RINSE THE PRODUCT CLEAN WITH CLEAR WATER. DRY WITH A SOFT COTTON FLANNEL CLOTH.
DO NOT: DO NOT CLEAN THE PRODUCT WITH SOAPS, ACID, POLISH, ABRASIVES, HARSH CLEANERS, OR A CLOTH WITH A COARSE SURFACE.