CHAPTER 3: INSTALLATION
Unpacking
APC has taken care to design robust packaging for your product. However, accidents and damage may occur during shipment.
Inspection
Inspect the UPS upon receipt. Notify the carrier and dealer if there is damage. The packaging is recyclable; save it for reuse or dispose of it properly.
Contents
The shipping package contains the UPS, one PowerView display bezel, three blank bezels, the mounting rail kit (containing the mounting rails, and hardware), one blank panel kit (containing five blank panels, screws and instructions), and a literature kit.
Placement
The Symmetra RM is designed for use in a data center or other office environment. Install it in a protected area that is free of excessive dust, corrosion, conductive contaminants, and has adequate air flow. Do not operate the UPS where the temperature and humidity are outside the specified limits.
Changes or modifications to this unit not expressly approved by the party responsible for compliance could void the warranty.
Installing the Symmetra RM
Installing the Symmetra RM is a
1.Position the Symmetra RM where it will be used. (This step includes mounting it in a rack if desired.)
2.Connect the Symmetra RM to its power source.
3.Wire the Emergency Power Off (EPO) switch.
4.Install modules into the Symmetra RM frame.
5.Connect equipment to the Symmetra RM.
This section describes each step in detail.
Position the Symmetra RM
Do not install the battery module(s) in the frame until you are ready to power up the Symmetra RM. Failure to do so can result in a deep discharge of the batteries, which may cause permanent damage.
Mounting rails are included with the Symmetra RM. The rails support the unit in the rack and provide adequate air flow.
The Symmetra RM requires two people to install due to its weight.
11