921013, 020, 023

3

4

1 2

OS7061

1.Chute Crank

2.Gear Cover

3.Control Panel

4.Hairpin

Figure 8

921019, 022

Install Discharge Chute and Discharge Chute Rod

(921017, 018)

(Figure 10, 11 and 12)

1.Grease underside of discharge chute ring (if not already greased).

2.Remove mounting hardware from auger housing (Figure 7).

3.Install discharge chute over opening in the auger housing. Finger tighten the mounting hardware removed in step 2.

NOTE: Leave discharge chute pedestal loose to help install the chute rod and connect it to the control assembly.

4.Remove the cover from the gear assembly on the discharge chute.

32

4

1

 

OS7060

1.Chute Rod

2.Gear Cover

3.Control Assembly

4.Hairpin

2 3

1.Chute Crank

2.Gear Cover

3.Control Panel

4.Hairpin

Figure 9

6.Orient the chute and pedestal to its most vertical position and tighten pedestal hardware to 15 – 31 lbf-ft (20 – 42 N•m) (Figure 7).

Figure 10

5.Release the lock teeth on the gear assembly with your finger and rotate the discharge chute 90° left.

6.Remove and save the hairpin from the control assembly underneath the control panel.

NOTE: Do not remove the hairpin installed on the chute rod.

NOTE: To ensure the discharge chute follows its full range of travel, make sure the control lever is pushed all the way to the left before installing and pinning the chute rod.

7.Align the holes on the end of the chute rod with the mark on the gear assembly and slide the end without a pin through the gear assembly, through the hook on the chute lock cable and into the hex hole in the control assembly.

IMPORTANT: The hook will prevent the control cable from contacting the engine or muffler guard.

GB - 10