Power Wiring Interconnections

All wiring must be the proper size, properly supported and protected by conduit. All wiring should be done per applicable federal, state and local codes, standards and regulations.

Complete the following connections between the transfer switch, power management system and main breaker panel. Also see the Wiring Decal on page 10.

WARNING

Low voltage wire cannot be installed in same conduit as power voltage wiring.

Failure to follow above warning could cause personal injury, damage and/or malfunction of equipment.

1.Set generator’s system switch to OFF position.

2.Set generator’s main circuit breaker to OFF (open) position.

3.Identify loads and their priorities (using list developed with owner) to be transferred to power management system in main breaker panel.

4.In main breaker panel, turn selected load circuit breakers to OFF position.

NOTICE

Improper installation can cause damage to the circuit boards and shorten their life. Installing circuit boards in live circuits will damage the board and is not a warranty condition. ALWAYS disconnect ALL sources of power prior to servicing.

Remove all power prior to installing this power management system. Failure to do so could cause internal damage to the board when making electrical connections.

Turn generator to OFF position.

Turn off utility power to the home standby generator and transfer switch.

5. Connect “GND” lug to an approved ground.

NOTE: Assure grounding electrode conductor is connected and bonded per applicable federal, state and local codes, standards and regulations.

6.Using installer supplied 300VAC or greater wire and supplied 1/4” double male, single female lugs, connect generator 240VAC from transfer switch to relay board in power management system.

7.Unplug current transformers from control module in transfer switch.

 

Green LED’s

Relay Board

Control

Module

 

 

Test

 

Button

 

Transfer Switch

 

Connections

Load

 

Connection

 

Wireways

Air Conditioner

Relays

Generator

Air Conditioner

Connection

Connections

To Transfer Switch

Ground Lug

To Air Conditioners