1.At hood location, install 2 x 4 cross framing between ceiling joists using dimensions shown.

2.Finish the ceiling surface. Be sure to mark the location of the ceiling joists and cross framing.

3.Position the support frame as shown. The UP ARROW should point towards the ceiling after installation.

4.Secure the support frame to joists and cross framing with four screws provided (6x70mm) and four washers (D. 6.4mm). Make sure screws are driven into center of joists and framing for maximum strength.

5.Adjust the overall height of the support frame. Loosen and re-tighten the 4 screws in the height adjustment slots as necessary. Insert 4 screws (3.9x9.5mm) and 4 washers (D.4.5mm) located in the Hardware Package.

Note that the hood height is 10-1/4” and that the bottom of the hood must be 24” min. and 30” max. above the cooktop.

DRYWALL

CROSS FRAMING

913/16

CEILING

JOISTS

WASHERS (Ø6.4mm)

MOUNTING SCREWS (6x70mm)

SUPPORT

FRAME

FRONT

HEIGHT ADJUSTMENT

SLOTS

TOP VIEW OF SUPPORT FRAME

107/8” (276mm)

713/16

(198mm)

CONNECT DECORATIVE FLUE

1.Secure the upper flue to the upper support frame with the mounting screws (3,9x9,5mm).

2.Insert the lower flue moving it completely towards the top and fix it temporarily with retaining screw (3.9x9.5mm).

INSERT THE LOWER

FLUE

RETAINING SCREW

MOUNTING SCREWS

(3.9X9.5MM)

UPPER FLUE

LOWER